MAINTENANCE

Repair and maintenance work on the drill shall only be performed by qualified personnel,
specifically trained on this equipment.
5.1

After operations

 Plug hydraulic hoses to prevent hydraulic leaks and dirt to enter the hydraulic system.
 Clean the tool with fresh water. Apply an anti-corrosive layer on the tool when it is clean,
WD40 or similar.
 Check hydraulic hoses, bolts, etc.
 Check the drill bit for damage.
 When stored make sure the cylinders is fully retracted, to avoid corrosion.
 Place tool in a proper storage box or room.
5.2

Periodic maintenance

 Start with "After operations" maintenance procedure.
 A careful review of the entire tool is mandatory. This includes a visual check of the tool with
hoses and a function test. Be sure that there is no leaks and that the feeding rate is correct.
 Replace or fix parts if needed. Damaged paint must be repainted.
Issue date:
2014.12.29
Rev.no:
002
Owner:
IKM Administrator
Company:
IKM Technique AS
Page 12 of 23