OPERATING PROCEDURE
6. Removing the compressor and 4-way valve
(1) Remove the cabinet and panels. (Refer to 1.)
(2) Remove the inverter assembly. (Refer to 2.)
(3) Recover gas from the refrigerant circuit.
Recover gas from the pipes until the pressure gauge
NOTE:
shows 0 kg/cm
(4) Detach the brazed part of the suction and the discharge pipe
connected with compressor.
(5) Remove the compressor nuts.
(6) Remove the compressor.
(7) Detach the brazed part of pipes connected with 4-way valve.
OBH767
(0 MPa).
2
Photo 9
Suction pipe
brazed part
61
PHOTOS
Discharge pipe
brazed part
Brazed parts of 4-way valve