9.
Once the VCB is in the switchgear compartment,
disengage the lift truck compartment interlock by rotating
the interlock pin counterclockwise, Figure 22, then move
the handle to the left and pull the latch handle toward
you and from the switchgear compartment until it is
fully retracted, Figure 23.
Figure 22. Rotate Interlock Pin Counterclockwise to Unlock the Latch Handle
Figure 23. Interlock Latch Handle
CAUTION
Verify that the VCB safety stop in the switchgear
compartment has returned to the normal
extended position.
10. Verify that the VCB safety stop has returned to the
extended position, Figure 24. If necessary, release by
inserting a screw driver into the slot to dislodge, Figure 25.
Figure 24. Stop in Proper Position
Figure 25. Eliminating Stop Interference
11. Release the lift truck floor lock by depressing the lever on
the right or left-hand side of the floor lock and move the
lift truck away from the switchgear, Figure 26.
Figure 26. Release Floor Lock