At first, mount two opposite swing posts to the junction, according to drawing. Raise the
unit by using an appropriate lifting gear.
Afterwards, mount the remaining two posts to the junction, place the whole unit into the
foundation holes and align item horizontally considering the play level marks on the inner
surface of the swing posts for installation depth.
Kaiser & Kühne Freizeitgeräte GmbH
Im Südloh 5 - 27324 Eystrup
detail junction
play level mark
6x screw connection per swing post consisting of:
[3400199] Hexagon screw M16x40 galvanized
steel
[3430019] Washer Ø 17mm
[3430053] Hexagon cap nut M16