7 Initial Start-up
7.1
Further information
7.2
40
7
Initial Start-up
7.1
Safety
Safety
The following instructions must be followed for safe machine commissioning.
Warning instructions are always given before a potentially dangerous action.
Basic safety instructions
1. Follow the instructions in chapter 3 'Safety and Responsibility'.
2. Commissioning may only be carried out by authorized personnel.
3. Before switching on, make sure that:
no one is working on the machine,
all access doors and panels are closed and secure.
Working on electrically conducting components.
1. Work on electrically conducting components may only be carried out by authorized electricians.
2. Switch off and lock out the supply disconnecting device and check that no voltage is present.
3. Check that there is no voltage on floating relay contacts.
Working on pressure systems
1. Close shut off valves or otherwise isolate the machine from the compressed air system to ensure
that no compressed air can flow back into the machine.
2. Vent all pressurized components and chambers completely.
3. Check all machine hose connectors with a handheld pressure gauge to ensure that all read zero.
4. Do not open or dismantle such valves.
Working on the drive
1. Switch off and lock out the supply disconnecting device and check that no voltage is present.
2. Do not open the enclosure while the machine is switched on.
Specification of authorized personnel is found in chapter 3.4.2.
Specification of dangers and their avoidance is found in chapter 3.5.

To be noted before commissioning

Incorrect or improper commissioning can cause injury to persons or damage to the machine.
Service Manual Screw Compressor