Water flows to the brine tank and at the same time down through the resin bed and up through the riser tube to drain, ensuring that all traces of brine are washed out and that the resin bed is compacted. The resin bed is now ready for the next service cycle. Erie Water Treatment Controls – Belgium Page 1...
The optimal bed expansion is generally obtained at a backwash flow of 1,8 L/min per dm of resin bed surface. Tank Backwash F.C. inch Gal/min (L/min) (6,1) (6,1) (7,6) (9,8) (13,2) (15,1) (18,9) (22,7) Erie Water Treatment Controls – Belgium Page 4...
(with plug ø 2,5 mm x 5,5 mm) into socket at the timers power lead and plug transformer into socket; the connection can be secured by means of the wire clip. Erie Water Treatment Controls – Belgium Page 6...
To adjust the residual hardness, the incorporated mixing valve must be regulated in function of the hardness of the incoming water and the desired residual hardness To increase the residual hardness: turn screw counter clockwise. To decrease the residual hardness: turn screw clockwise. Erie Water Treatment Controls – Belgium Page 7...
In the event of a timer failure, the display will show the message: Service Required In such case, entering one of the programming levels can possibly solve the problem. However if the problem persists, professional service is required. Erie Water Treatment Controls – Belgium Page 8...
Page 13
If the control valve is left in this position, the countdown timer will countdown to 0 sec and start a regeneration. To cancel this mode, press the scroll button before the countdown timer has reached 0 sec; the control valve will return to the service mode. Erie Water Treatment Controls – Belgium Page 9...
3. Press the scroll button again; the display will show: Set hardn.: XX°f Press the up button or down button to set the water hardness of the incoming untreated water. Erie Water Treatment Controls – Belgium Page 10...
Page 15
Press the up button or down button to set the model of flow meter used: SNAP SENSOR: model with snap-on flow meter sensor. SCREW SENSOR: model with sensor fixed by means of screw. Erie Water Treatment Controls – Belgium Page 11...
Page 16
11. Press the scroll button again; the display will show: Exit Press the up button or down button to save the program to the NOVRAM® and exit the programming level. Erie Water Treatment Controls – Belgium Page 12...
4. Remove the screws holding the PCB in place. 5. Push aside the clip holding the PCB in place and remove the PCB. 6. Reverse the procedure for reassembly; refer to wiring diagram for proper lead connections. Erie Water Treatment Controls – Belgium Page 14...
16. Lower the valve cover straight down onto the valve body and press it down firmly and evenly to seat the valve cover. 17. Install the 6 bolts and tighten them in a cross pattern. 18. Install the drain hose to the drain line fitting. Erie Water Treatment Controls – Belgium Page 15...
4. Use silicone base lubricant to lubricate the green side of the seal disk. 5. Install the seal disk in the valve body, with the green side facing up. 6. Reverse the procedure for reassembly; refer to Parts Replacement “Rotor Assembly”. Erie Water Treatment Controls – Belgium Page 16...
9. Install the timer head assembly to the valve body and tighten the 2 back plate mount screws. 10. It is now necessary to check the synchronisation of valve body and timer; refer to Parts Replacement “Synchronising valve body and timer head”. Erie Water Treatment Controls – Belgium Page 17...
6. Lower the valve cover straight down onto the valve body and press it down firmly and evenly to seat the valve cover. 7. Install the 6 bolts and tighten them in a cross pattern. 8. Install the drain hose to the drain line fitting. Erie Water Treatment Controls – Belgium Page 18...
Page 23
2400VS SERIES Erie Water Treatment Controls – Belgium Page 19...
6. Not enough water in brine tank 6. Refer to problem “Control valve fails to refill brine tank” Control valve cycles continuously Cause Solution 1. Defective or shorted micro switch 1. Replace micro switches Erie Water Treatment Controls – Belgium Page 20...
Page 25
1. Verify that flow control is installed and correctly sized control 2. Lower and/or upper distributor 2. Replace distributor(s) damaged 3. Leak between riser tube and upper 3. Verify that riser tube is seated correctly and is not cracked distributor Erie Water Treatment Controls – Belgium Page 21...
Page 26
3. Replace drive motor 4. Valve body and timer out of 4. Synchronise valve body and timer synchronisation 5. Leak between rotor and seal disk 5. Verify or replace rotor and seal disk Erie Water Treatment Controls – Belgium Page 22...
4. Verify correct functioning of flow meter; clean impeller if necessary. 5. Verify programming of timer; re-program timer if necessary. 6. Measure the residual hardness; adjust mixing valve if necessary. 7. Verify min and max. pressure; install pressure reducer if necessary. Erie Water Treatment Controls – Belgium Page 23...