Fixed Hoist Test Facility Operation and Maintenance Manual
Start Up
1. Install Hanging Hoist Mount, Arm using the pins and retaining pins
2. Install hoist on mount using the pins and retaining pins
3. Raise mount into position, install the pins in the load cells, lower chain hoist to apply
the load to the lead cells
4. Attach the Electrical harness connectors
5. Attach the 400Hz power cable to the receptacle
6. Turn on the 3 phase 400 hz power switch
7. Position the Zephyr RHGSE under hoist
8. Turn the Power switch on the control box to on, the load indicator should illuminate
9. Activate the hoist select switch on the control box to select the BL-29900 hoist
10. Press the Tare button on the load display to zero out the load with no load on the
cable
11. Operate the hoist using pendant, or pilot override
12. Attach the rescue hoist cable to the Zephyr RHGSE and operate the hoist in the
down direction
13. Follow the operating instructions for the Zephyr RHGSE while running the hoist
Zephyr International LLC *5015 Enoch Rd, Conway SC 29526 * Phone 843-365-2675 *Fax 843-365-2677
Email
Operating Procedure
zephyradmin@zephyrintl.com*
Serving Helicopter Rescue Hoist Users Worldwide