GOLD GV Series 3 & 4 — Venting Supplement for 3.00" venting
Installation — assembly
Finish the vent installation
Installing condensate tubing
1.
See Figure 11 to install condensate tubing (provided
by others). Use condensate pump if floor drain is
higher than condensate drain on boiler.
If required:
2.
Size pump in gal/hr (boiler model):
Refer to pump manufacturer's instructions. Drain
to a non-freezing area.
If vent pipe or combustion air pipe must be reassembled
When vent pipe or combustion air pipe is disconnected for any reason, it must be reassembled and resealed
according to this Venting Supplement, the direct vent termination kit instructions and the vent pipe manufacturer's
instructions.
8
use a low-profile pump — OR —
set boiler on foundation (see GV Boiler
Manual) to allow gravity flow to discharge.
0.78 (GV-3)
1.17 (GV-4)
1.56 (GV-5)
1.95 (GV-6)
Sealant recommended by vent pipe manufacturer must be used as indicated in their instructions.
Vent and combustion air connector piping must be sealed gas-tight to prevent possibility of flue
gas spillage and carbon monoxide emissions, resulting in severe personal injury or death.
continued
Figure 11 Installation of condensate tubing
Part number 550-141-923/0710