Scenario 3: Cabinet/Rack Mounting
Before You Start
An S600-E series chassis is 1 U high, and its width is standard. It can be installed in a standard 19 inch
cabinet/rack.
The cabinet/rack must have reliable ground points to ground the switch.
A separately purchased non-standard cabinet/rack must have sufficient space for chassis installation.
Install a mounting bracket on the other side in the same way.
The captive screws and M6 screws are not delivered with the switch and need to be separately purchased if
needed.
The length of three adjacent mounting holes may not be 1 U. Observe the scale ticks on the mounting rails
when installing floating nuts.
Installation Procedure
Step 1
Secure mounting brackets to the chassis with M4 screws.
Step 2
Install four floating nuts on the front mounting rails, two on each side. Leave a distance of 1 U between
the two floating nuts on each mounting rail.
Step 3
Hold bottom of the chassis and move the chassis into the cabinet/rack.
Step 4
Use M6 screws to secure the chassis onto the cabinet/rack.
Step 5
Connect the ground cable. Connect the M4 lug (with a smaller hole) to the ground point at the rear of
chassis and the M6 lug (with a larger hole) to the ground point on the cabinet/rack.