Unpack The Crate; Position The Boiler - Burnham ES2 ES2 Installation & Service Instructions Manual

Enhanced series 2 gas - fired boiler
Table of Contents

Advertisement

THE BOILER IS TOP-HEAVY. Do not
allow it to tip over.
Remove the sleeve.
1.
Remove the contents from the skid, except
2.
the boiler.
Remove the four (4) hex-drive lag screws
3.
holding the boiler to the skid (Figure 1-a).
1-a
OBSERVE MINIMUM CLEARANCES to
combustible walls and ceilings to avoid potential
fire hazard.
DO NOT INSTALL ON CARPET. This may cause
a fire.
INSTALLING THE BOILER NEAR A SOURCE OF
FLAMMABLE LIQUIDS or gases may cause fire or
explosion.
Slide the boiler into desired location.
1.
Meet the minimum clearances to
2.
combustible construction per the
Specification Section of this manual.

1. UNPACk THE CRATE

2. POSITION THE BOILER

WARNINGS
CLEAN BURNERS DAILY if operating the boiler in
a dusty environment.
PROTECT IGNITION SYSTEM COMPONENTS
from sources of water that may spray, drip, or rain
on them during installation or service.
Tip the boiler and shimmy it off the skid.
4.
1-b
Allow 24" service clearance in front and on
3.
the left side of the boiler.
Level the boiler, using shims as necessary.
4.