Page 4
1. Hardware: Required court properties to install interactiveRACQUETBALL: Requirements: Dedicated Power Outlet Active Internet Connection Console Mounting Space Ceiling Load-Bearing 100kg/220lbs or Stand Load-Bearing 100kg/220lbs Floor and Ceiling Spaces to integrate the Sensor Bars Cable Ducts Wall Spaces for Cameras...
2. Installation: First delivery: Second delivery: Console mounting plate Console Front Wall Paint Sensor Bars Cameras Main Cable The system will be installed and activated by our team or you will get remote installation support. Installation Steps: Check delivered components Check already sent components before for court preparation Check court measurements Check internet and power plug...
Page 7
2. 2. Check already mounted components before installation: The front wall should always be painted with our white paint. The console mounting plate (1) should already be fixed (load-bearing 100kg/220lbs) on the ceiling before starting installation. The console can also be placed on a stand (load-bearing 100kg/220lbs). Make sure that the console is placed in middle at the rear of the court at the most up position.
Page 12
2. 6. Installation Console: Set anchor on the holding plate for the rope/chain hoist to lift up the console. Secure the chain hoist to the console metal structure. With the help of a scaffold, accompany the console as it’s being lifted up. Secure the console to the holding plate.
Page 16
2. 7. Mount Sensor Bar Top: Start with sensor part number 1 from the left side. Remove the covers and mount the sensor bar flush into the ceiling directly in the connection to the front wall. Secure the green plugs (1) and run the cables through the cable duct behind the front wall to the sensor bar bottom. Mount the covers. Reference video links (interactiveSQUASH): ●...
Page 17
2. 8. Mount Sensor Bar Bottom: Start with part no. 1 from the left side. Remove the covers and mount the sensor bar flush into the floor directly in the connection to the front wall. Reference video links (interactiveSQUASH): ● 10_Sensor tin bottom mounting ●...
Page 20
2. 9. Connect Sensor Bars: When all tins are installed - Perform the calibration steps: Switch up the PIN 3 on all LVXs (green board) Unplug the power supply by disconnecting the main cable going in the y-splitter. Plug back in the power supply. Switch down the PIN 3 on all LVXs Unplug the power supply.
2. 10. Install cameras: Position front cameras. The camera housing measures 6.1 x 6.1 inch. The distance from the center (1) of the camera housing to the side walls is 31.5 and to the floor 9.22 inch. The distance from the outer edge (2) of the camera housing to the side walls is 28.44 and to the floor 6.17 inch. Reference video links (interactiveSQUASH): ●...
Page 23
2. 10. Install cameras: Open the camera housing by removing the front glass. Mount the cameras flush into the walls and ceiling. Use the long holes (1) to fix the metal housing with screws. Bring the LAN cable through the hole (2), open the internal camera by 3 security screws (tool is in the boxes) and connect (3) the camera. Connect the LAN cables of the cameras with internet switch located in the console (4).
2. 11. Projector Adjustment: Using focus, adjust the projector's focus to the point that it's as sharp and accurate as it gets. Using Zoom and Shift, adjust the projection to cover the entire front wall. You’re now all set for the final installation stage of your interactiveSQUASH system. Once you’ve mounted all our hardware, our technical team is ready to support the setting of the hardware.
Page 25
2. 12. Hardware adjustments with setup: After all hardware mounting is done, your system will get set up for use. Our technical support will guide you on video / audio how to set all devices. Hardware adjustments include IR camera focus, IR lights setting. Checking the difference images &...
Need help?
Do you have a question about the interactiveRACQUETBALL and is the answer not in the manual?
Questions and answers