Necessary Tools And Instrument List For Installation - Hitachi CH-Box Installation Manual

For cooling / heating change-over box
Table of Contents

Advertisement

CH-AP16MSSX
JCH-AP16MSSX
G (High/Low Pressure)
G (Low Pressure)
2
L
S S
S
S
S
2
L
L
L
G
G
G
Unit P
Unit O
Unit N
Mark
Electronic Expansion Valve
1
2
Strainer
2.3 Necessary Tools and Instrument List for Installation
No.
1
Handsaw
2
Phillips Screwdriver
3
Vacuum Pump
4
Refrigerant Gas Hose
5
Megohmmeter
6
Copper Pipe Bender
7
Manual Water Pump
8
Pipe Cutter
9
Brazing Kit
10
Hex Wrench
NOTE:
Use tools and measuring instruments (vacuum pump, refrigerant hose, charging cylinder, and manifold
gauge) exclusively for the refrigerant R410A.
P5417025-rev.1
Outdoor Unit Side
S
S
S
S
L
L
L
L
G
G
G
G
Unit M
Unit L
Unit K
Unit J
Indoor Unit Side
Part Name
Figure 2.5 Refrigeration Cycle Diagram
Tool
1
S
S
S
S
L
L
L
L
G
G
G
G
Unit I
Unit H
Unit G
Unit F
G
L
No.
11
Wrench
12
Charging Cylinder
13
Manifold Gauge
14
Wire Cutter
15
Gas Leak Detector
16
Level
17
Crimper for Solderless Terminals
18
Hoist (for Indoor Unit)
19
Ammeter
20
Voltage Meter
S
S
S
S
L
L
L
L
G
G
G
G
Unit E
Unit D
Unit C
Unit B
: Refrigerant Gas Pipe Connection
: Refrigerant Liquid Pipe Connection
: Field Refrigerant Piping
: Flare Connection
: Brazing Connection
: CH-Box
Tool
S
L
G
Unit A
5

Hide quick links:

Advertisement

Table of Contents
loading