Page 1
Instructions for setting up a new REFUsol 20K-2T, REFUsol 33K-2T & REFUsol 50K-3T...
Page 2
General Before the commissioning of an inverter, the following parameters need to be set: Date ✓ Time ✓ ✓ Country Code This is done through the display and following specific steps. SetUp a new REFUsol 20K-2T / 33K-2T / 50K-3T_EN_2021.02.05...
Page 3
Minute: Up arrow 45 times → 45 → ΟΚ → minutes appear → OK Seconds: Up arrow 20 times → 20 → ΟΚ → seconds appear → OK Message success appears SetUp a new REFUsol 20K-2T / 33K-2T / 50K-3T_EN_2021.02.05...
Page 4
Up arrow→ 0 → ΟΚ → Up arrow 1 time → 1 → ΟΚ → Up arrow 3 times → 3 → ΟΚ Code 013 is created → press ΟΚ → message “success” appears SetUp a new REFUsol 20K-2T / 33K-2T / 50K-3T_EN_2021.02.05...
Page 5
Inverter under operation After setup is completed, inverter with go into activation mode. At the display message “Check” appears and countdown until connection. Once inverter goes into successful operation the message “Normal” appears. SetUp a new REFUsol 20K-2T / 33K-2T / 50K-3T_EN_2021.02.05...
Page 6
Inverter’s information At the stick at the right side of inverter you can find inverter’s characteristics and the Activation Code for portal REFUlog (www.refu-log.com), its’ serial number and firmware version. Example: • Activation Code: 7CBDFF11FF11-6BFC-SL1ES033L3L958 Seral Number: SL1ES033L3L958 • Firmware (Software): V2.20 •...
Need help?
Do you have a question about the REFUsol 20K-2T and is the answer not in the manual?
Questions and answers