5. ASSEMBLY
NOTE: The mobile scaffold tower may only be assembled, used
and dismantled by persons familiar with these Assembly and Use
Instructions.
NOTE: These instructions show the assembly of SSCL1 +
SSCL3 + SSCL4 from scratch. If you already have SSCLI +
SSCL3 assembled it will be necessary to partly disassemble
some of the upper parts so that it resembles diagram No.8 above.
The parts removed will be reused in the assembly of the
extended tower.
5.1
Open folding base A and insert the locking pin in the centre of
the folding section. Place diagonal B on one side on the first rung
and on the 4th rung on the other side. Make sure that the
butterfly locking part is completely rotated to hold the diagonal
firmly in position.
5.2
Place horizontal brace C on the first rung and lock in position.
5.3
Take 2 of the 6 rung end frames, F and 3 diagonals B. Position a
diagonal on the topmost rung of one frame and the second
diagonal on the same frame on the second rung on the other
side. The last diagonal is to be placed on the top rung of the
second end frame (WARNING : Make sure that everything is
the right way round as per the sketch!)
5.4
Before climbing within the frame, lock the wheels. Position
the end frames on to the folding base and lock the lower diagonal
B to the 5th rung of the base frame. Make sure that the butterfly
locking part is completely rotated to hold the diagonal firmly in
position. Put the 4 locking pins in place.
5.5
Position the 4 stabiliser legs G as per the heights indicated on
the sketch. Tighten firmly at the correct angle as shown above.
Note: Not all stabiliser legs illustrated.
5.6
Position platform H on the 5th rung from the bottom.
5.7
Climb through the trapdoor, sit on the edge and position the two
horizontal braces C on the 7th rung from the bottom and the 2
braces C on the 9th rung. Lock the snaplocks firmly in position.
5.8
Stand up on the platform and fix the 2 diagonals B hanging from
the frames into position.
Original Language Version
SSCL4
Issue No.1 - 08/06/10