Page 1
DEFRA SCHIEDEL INSTALLER EXEMPT REWARDS Isokern Celsius Installation instructions DON'T FORGET TO REGISTER YOUR INSTALLATIONS AND START EARNING SCHIEDEL INSTALLER REWARDS See inside for more details www.schiedel.com/uk SAP Issue 1 - 940003850 - October 2020...
Page 2
In general • The installation instructions must be followed in order to comply with the guarantee of the system and we recommend that it is installed by a HETAS Approved Installer. • The installer must inspect and test the finished system and leave the completed notice plate and results from the test with the householder.
Distance requirements: When choosing a location, consider the illustrations below and the distances to combustible materials. 0 mm to combustibles 300 mm 300 mm Ventilation grill Inset opening Min. 1100 mm to combustibles Insert opening Ventilation grill When installing against non-combustible material, the requirements of the building regulations must be followed.
Recommended chimney draft 12 Pa 0036 Schiedel Skorstene ApS Industrivej 23 · DK-7470 Karup CPD 90219 001 DK014 DOP 23082019 DS/EN 13240/A2:2004 Schiedel Isokern Celsius Schiedel Isoke Nominal heat output: 6,7kW CO emission at 13% O²: 0.082% installed within installed within an...
Page 5
The foundation should be at least a 100mm thick reinforced concrete slab. LIP GLUE FOR THE PUMICE COMPONENTS Schiedel ISOKERN Chimney Adhesive is used for the construction of all the Pumice elements within the frame and chimney. The mixing instructions are shown on the packaging.
Page 6
Assembly Measure and note the desired Apply glue to the whole top Apply glue to the module outer location of ISOKERN CELSIUS surface of the module before edge, with the exception of the gap solution. Apply Schiedel ISOKERN placing the the next block.
Page 7
Assembly Glue the 3 metal plates onto the Apply glue around the edge and Apply glue to each block edge, base plate within the opening for place the first top section above with the exception of the gap for the insert so they lie under the the opening.
Page 8
Assembly The door is removed first (the Remove the 2 thin cover plates, Now slide the appliance into door can be lifted off at approx. 10 to get access to the adjustable position and adjust and fix using cm open position). feet (bolts) at the bottom.
Page 9
Assembly The Octagonal stainless steel The first outer chimney block is The octagonal pumice starter adaptor slides down inside glued into place, making sure it’s flue block fits inside the octagonal the stainless steel pipe shown square and level. stainless steel adaptor. previously.
Page 10
Assembly Code 4 lead flashing to be fitted at roof level as per Building Regulations. We recommend that you scorch a 5-10mm deep channel into the outer surface of the 10mm gap for ventilation casings and fold in the top edge of the flashing. under Top Ring Finish the outer surface of the casings above the roof with 2 part waterproof render.
Page 11
The Schiedel Installation App Download the app today, as it offers a number of very useful guides on all aspects of installing an appliance using Schiedel Chimney Systems, including: • Quick and straightforward reference for installers. • Video breakdowns of each stage of the installation process, from connection to the appliance through to termination.
Page 12
Schiedel Chimney Systems Ltd. Unit 8 & 9, Block A, Holton Road Holton Heath Industrial Estate Poole, Dorset BH16 6LG Tel. +44 (0)1202 861650 sales.uk@schiedel.com | www.schiedel.com/uk...
Need help?
Do you have a question about the Isokern Celsius and is the answer not in the manual?
Questions and answers