Wiring The Ups; Final Assembly - Riello Socle Box Installation Manual

Advertisement

W
UPS
IRING THE
The Socle Box is equipped with different openings on its various sides and an inner holed bar to simplify
the wiring operations of the UPS.
A –
fixed opening for the passage of wires coming from the UPS.
Upper
B – Recloseable windows on both sides. Designed to facilitate working inside the Socle Box and to
allow the passage of wires from the rear part if necessary.
C – Mobile lower window for the passage of wires, equipped with adjustable closure, depending on
needs.
D – Holed bar to allow tightening the wires which pass through the Socle Box using simple clamps. The
bar can be raised/lowered using the dedicated fastening holes on the sides, as shown in figure (see
d1). Each of these holes can be used for grounding the Socle Box using a screw present on one of
the side bars (see d1).
F
INAL ASSEMBLY
Once the UPS wiring is complete and any windows not used by the Socle Box have been closed, proceed
with securing the UPS using the 2 side fixing brackets and the 8 galvanised M6x8 screws supplied.
Assemble the front bulkhead using the 8 black M4x8 screws supplied.
The structure thus obtained is stable as a whole and post-installation handling operations can be carried
out safely; but if environmental circumstances or supply requirements require the ups be fixed to the
ground, use the two L-shaped brackets supplied with the Socle Box to secure it to the ground.
6