ALLURE
A L L U R E ™ A L U M I N I U M L O U V R E - P AT I O I N S TA L L AT I O N G U I D E
BEFORE YOU START
Carefully read these instructions and refer to them constantly during each stage of construction. If you do not have all the necessary tools or information,
contact Stratco for advice. Before starting, layout all components and check them against the delivery docket. The parts description identifies each key part,
and the component layout diagram indicates their fastening position.
Double check all dimensions, levels and bolting locations before cutting, screwing or bolting structural members. It is recommended that the installers erecting
the structure have had some previous building experience because some modifications to the existing house structure may be required. If a freestanding unit
is being installed, the attachment beam becomes the rear fascia beam and is installed as per the details for the front fascia beam. Box gutters and flashings do
not need to be pre-fixed until all beams have been erected.
TOOLS REQUIRED
•
Drill and Hex-Head Adaptor
•
Rivet Gun
•
Tape Measure
•
Tin Snips
•
Spirit Level
Note: All screws within the unit must be fastened by hand using a screw-driver, or a low-torque, low-speed drill.
Using a powered tool may result in screw heads shearing from the shank. If screw heads shear from shank it is recommended
that a Screw Extractor kit is used to remove the screw.
Note: Allure components are designed for 1° fall to accommodate the minimum required louvre fall and Allure
construction should allow for this. A minimum 1:200 fall shall be maintained during construction for gutter fall toward
INSTALLATION GUIDE
™
•
Post Hole Digger
•
Silicone Gun
•
Spanners or Ratchet
•
Adjustable Construction Props
•
Concrete
downpipes when this is perpendicular to louvre direction.
•
Ladder
•
Vise Grips
•
Countersinking Drill Bit
•
Phillips-Head Screwdriver
•
Hole-Saws (ø13mm & ø16mm)
Need help?
Do you have a question about the ALLURE and is the answer not in the manual?
Questions and answers