Carefully read these instructions and refer to them constantly during each stage of construction. If you do not have all the necessary tools or information contact Stratco for advice. Before starting, lay out all components and check them against the delivery docket. The component description identifies each key part and the component layout diagram indicates their fastening position.
COMPONENT DIAGRAM COLUMN 68 PURLIN BRACKET RIGHT HAND SHS CONNECTOR CHECKED-IN PURLIN BRACKET INLINE SHS CONNECTOR 68 OUTBACK PURLIN LEFT HAND SHS CONNECTOR GUTTER 150 OUTBACK BEAM LEFT HAND GUTTER STOPEND 5° RAFTER BRACKET (LOW) RIGHT HAND GUTTER STOPEND 5° SUSPENSION BRACKET BEAM END CAP 120 OUTBACK RAFTER ROOF CLADDING...
Page 4
STRATCO OUTBACK SKILLION INSTALLATION GUIDE BACK CHANNEL INSTALLATION ATTACHING TO A BRICK WALL When fixing the back channel to a brick wall, pre-drill the The short edge of the back channel is the underside. The back anchor holes using a masonry drill bit. Attach the back...
Page 5
ATTACHING TO A STRUCTURE FRAMEWORK ERECTION WALL ATTACHMENT END RAFTER BEAM (120 OUTBACK RAFTER) For units attached to a wall, position the 5° Rafter Suspension When installing all beams, ensure the double thickness of Brackets where the beams meet the wall. The top tab of the the beam is on top.
Page 6
STRATCO OUTBACK SKILLION INSTALLATION GUIDE PURLINS Rafter to sit flush Rafter (120 Outback Beam) with fascia beam Purlins can be installed in between, or over the rafters. Purlins installed between rafters (checked-in purlins), are secured with 68mm Purlin Brackets and Checked-In Purlin Brackets Fascia Beam over the intermediate rafters.
Page 7
50x50mm SHS column COLUMNS AND FOOTINGS reinforcement 68 Outback column 30mm If fixing the columns into the ground, dig the holes to the specified size. Place a half brick in the bottom of the hole (Figure 4.0). Measure from the underside of the beam to the top of the half brick and cut posts to this length at each post location.
Page 8
STRATCO OUTBACK SKILLION INSTALLATION GUIDE FOOTING PLATES 50mm SHS Footing brackets are available if the posts are to be fixed to an existing concrete slab. Establish the column lengths by measuring the distance from the underside of the fascia beam to the concrete slab, less the thickness of the footing Two 12x20mm hex head screws plate (or 20mm for Outback footing plate).
Page 9
ROOFING TURNING UP THE ROOFING ENDS Back Channel While still at ground level the valleys on the high end of the roof decking need to be turned up using a turn-up tool or Roof Sheet adjustable spanner to aid in weather proofing (Figure 6.0). At the low end of the sheets the valleys of each corrugation should be turned down into the gutter using a turn up/down tool or adjustable spanner.
Page 10
STRATCO OUTBACK SKILLION INSTALLATION GUIDE GUTTER ASSEMBLY CAPPING & FLASHING To prevent moisture from entering the beams and for GUTTER PREPARATION aesthetics, any beams with exposed ends require end caps To establish the gutter length, measure the length of the to be fitted.
Page 11
Do not allow soil to remain in permanent contact with the columns as corrosion will result in the base of the column. Refer to the ‘Selection, Use and Maintenance of Stratco Steel Products’ brochure for complete details of the maintenance requirements.
Refer to the ‘Selection, Use and Maintenance’ brochure for more information. « SCAN THIS QR CODE TO FIND A STRATCO NEAR YOU 1300 155 155 stratco.com.au All brands and logos/images accompanied by ® or ™ are trade marks of Stratco (Australia) Pty Limited. ® Copyright October 2020...
Need help?
Do you have a question about the OUTBACK SKILLION and is the answer not in the manual?
Questions and answers