Installation preparations

3.9.1 IT infrastructure
How the terminal is installed and configured depends on the existing IT
infrastructure, which can vary from company to company, particularly with regard
to network security guidelines.
Prior to installation, any IT-relevant queries must be clarified with the customer's IT
department. The following checklists are intended to assist when clarifying queries:
Check
1)
Is the terminal being used in a DNS
Server environment or only with
DHCP?
2)
Are there any naming conventions
for the connection of network
devices to the corporate network?
3)
Is the terminal operated with a
static IP address?
4)
The following ports are used for
network communication:
- TCP 20, TCP 21 (note the FTP for
parameters)
- TCP 80 for normal communication
- UDP 1900 SSDP protocol
5)
The following ports are used for
local (client) communication:
- TCP 1433 SQL communication
- TCP 1099 JAVA
- TCP 3001 and TCP 3005 BCOMM
JAVA
6)
Can Java be installed on a local
computer?
14
Measures
Refer to settings when configuring B-
COMM Java (Ch. 5.4.2)
If there are, the Kaba standard name
must be adjusted manually in the
terminal before starting the
installation and configuration process
(Ch. 6.4.4)
If operation is with a static IP address,
this must be set manually in the
terminal before starting the
installation and configuration process
(Ch. 6.4.5)
Ports must be enabled by IT.
Ports must be enabled in the Windows