H3C S7500 Series Installation Manual
H3C S7500 Series Installation Manual

H3C S7500 Series Installation Manual

Hide thumbs Also See for S7500 Series:

Advertisement

Quick Links

Installation Manual
H3C S7500 Series Ethernet Switches
Appendix B N68 Cabinet Installation...........................................................................................B-1
B.1 Installing N68 Cabinets .....................................................................................................B-1
B.1.1 Installation Overview...............................................................................................B-1
B.1.2 Requirements for Space Planning ..........................................................................B-2
B.1.3 Installation Preparation ...........................................................................................B-3
B.1.4 Installation Procedure .............................................................................................B-5
B.2 Installing Cabinets on Cement Floor .................................................................................B-6
B.2.1 Installing Cabinets with Feet...................................................................................B-6
B.2.2 Installing Cabinets without Feet............................................................................B-22
B.3 Installing Cabinets on Antistatic Floor .............................................................................B-32
B.3.1 Introduction to Supports and Guide rails ..............................................................B-32
B.3.2 Installation Procedure ...........................................................................................B-36
B.3.3 Positioning Supports.............................................................................................B-38
B.3.4 Installing Supports ................................................................................................B-41
B.3.5 Installing Antistatic Floor Accessories ..................................................................B-46
B.3.6 Leveling the Cabinets ...........................................................................................B-46
B.3.7 Fixing Cabinets .....................................................................................................B-48
B.3.8 Testing Insulation..................................................................................................B-50
B.3.9 Restoring the Floor ...............................................................................................B-50
B.3.10 Verifying Installation............................................................................................B-52
B.4 Installing Cabinet Accessories ........................................................................................B-53
B.4.1 Installing Feet........................................................................................................B-53
B.4.2 Installing Doors .....................................................................................................B-56
B.4.3 Installing Protection Ground Cables .....................................................................B-60
B.5 Introduction to Cabinet Cable Management....................................................................B-61
B.5.1 Introduction to Cabinet Grounding Points.............................................................B-61
B.5.2 Introduction to Cabinet Power Distribution ...........................................................B-62
B.5.3 Introduction to Internal Cable Management .........................................................B-66
B.6 Remodeling Cabinets ......................................................................................................B-73
B.6.1 Remodeling an S7500 N68-18 Cabinet................................................................B-73
B.6.2 Remodeling an S7500 N68-22 Cabinet................................................................B-76

Table of Contents

i
Table of Contents

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the S7500 Series and is the answer not in the manual?

Questions and answers

Summary of Contents for H3C S7500 Series

  • Page 1: Table Of Contents

    Installation Manual H3C S7500 Series Ethernet Switches Table of Contents Table of Contents Appendix B N68 Cabinet Installation...................B-1 B.1 Installing N68 Cabinets .....................B-1 B.1.1 Installation Overview....................B-1 B.1.2 Requirements for Space Planning ................B-2 B.1.3 Installation Preparation ...................B-3 B.1.4 Installation Procedure .....................B-5 B.2 Installing Cabinets on Cement Floor .................B-6...
  • Page 2: Appendix B N68 Cabinet Installation

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Appendix B N68 Cabinet Installation B.1 Installing N68 Cabinets B.1.1 Installation Overview Note: Two types of N68 cabinets are available. One is 1.8 meters high, with a headroom of 37 U;...
  • Page 3: Requirements For Space Planning

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.1.2 Requirements for Space Planning Before installing the cabinet, you need to plan installation space first. Sufficient space must be provided in front of and at the back of the cabinet for maintenance. Figure B-2 describes the planning of installation space for a single cabinet.
  • Page 4: Installation Preparation

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.1.3 Installation Preparation Follow the given steps to do the installation preparation: Draw lines correctly to avoid rework. Unpack the cabinet and the cabinet accessories according to the operation guide.
  • Page 5 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Support bar Figure B-4 Remove support bars...
  • Page 6: Installation Procedure

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.1.4 Installation Procedure Note: The weight of an empty N68-22 cabinet is 160 kg (352.7 lb.) and that of an empty N68-18 cabinet is 120 kg (264.6 lb.). Before installing the cabinets, you must check load-bearing capacity of the floor as required.
  • Page 7: Installing Cabinets On Cement Floor

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.2 Installing Cabinets on Cement Floor This section describes how to install N68-22 cabinets on cement floor. The dimensions of an N68-22 cabinet are 2200 x 600 x 800 mm (86.6 x 23.6 x 31.5 in.) (H ×...
  • Page 8 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Bolt M12×70 (2) Spring washer 12 (3) Big flat washer 12 (4) Insulation washer (5) Anchor plate (6) Insulation pad of the anchor plate (7) Expansion tube...
  • Page 9 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Fastening nut for cabinets (2) Fastening nut for anchor plate (3) Leveling nut (4) Foot Figure B-7 Foot components Installation procedure Figure B-8 illustrates the procedure for installing N68-22 cabinets on cement floor.
  • Page 10 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Start Start Position the cabinet Locate the cabinet Level the cabinet Level the cabinet Level the cabinet Level the cabinet Combine cabinets Combine cabinets Combine cabinets Combine cabinets...
  • Page 11 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Table B-1 Determine installation hole positions based on the layout Step Operation Remarks Figure B-9 shows installation positions of the expansion Determine the installation positions of the bolts and feet for a single expansion bolts according to the cabinet.
  • Page 12 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Hole for fixing an expansion bolt (2) Mark for positioning feet (3) Cabinet outline (4) Inner wall or reference body Figure B-10 Installation positions of the expansion bolts and feet used to combine a...
  • Page 13 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Figure B-11 Marking template (only for installation on cement floor) Drill holes. Use M12 expansion bolts to fix supports on the ground. Use a percussion drill with Ф16 bit to drill holes.
  • Page 14 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Prior to installation, clean dust inside and outside the holes with a dust collector and then measure the spacing of holes. If errors are not acceptable, you must position and drill the holes again.
  • Page 15 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Leveling nut Figure B-13 Level a cabinet Fasten cabinet feet. Fasten all the nuts used for fastening cabinets on all the feet so that the nuts for fastening cabinets can be against the nuts on the holder, as shown in Figure B-14.
  • Page 16 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Welded nut on the foot holder (2) Nut for fastening the cabinet Figure B-14 Fasten feet III. Fixing the cabinets Caution: When combining two or more cabinets, you have to combine the cabinets first, and then fix anchor strips.
  • Page 17 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Caution: Anchor plates must be installed according to the direction indicated by the arrow in the following figure. Figure B-15 Install anchor plates (on cement floor) Install insulation components and fix anchor plates.
  • Page 18 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Bolt M12×70 (2) Spring washer 12 (3) Big flat washer 12 (4) Insulation washer (5) Insulation pad of the anchor plate (6) Expansion tube (7) Expansion bolt...
  • Page 19 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Connecting plate for combining cabinets Figure B-17 Position of the connecting plate Remove the connecting plates from the adjacent cabinets, and then reinstall the connecting plates, as shown in Figure B-18.
  • Page 20 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Nut M8 (2) Flat washer 8 (3) Combined screw M6x12 (4) Spring washer 8 (5) Bolt M8x30 (6) Connecting plate for combining cabinets Figure B-18 Install the connecting plate for combining cabinets Caution: M8x30 bolts used to combine cabinets are delivered together with support accessories.
  • Page 21 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Figure B-19 A single cabinet installed on cement floor B-20...
  • Page 22 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Figure B-20 A row of cabinets installed on cement floor V. Verifying installation The following requirements must be satisfied: Cabinet arrangement, installation positions, and directions must satisfy the requirements of the construction design.
  • Page 23: Installing Cabinets Without Feet

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation The surface of the entire row of cabinets should be on the same plane. Adjacent cabinets should be closely arranged. B.2.2 Installing Cabinets without Feet Figure B-21 illustrates how to install N68-22 cabinets without feet on cement floor.
  • Page 24 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Note: The procedure of combining cabinets is optional. When two or more cabinets need to be installed in the same row, they should be installed side by side.
  • Page 25 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation ≥800 ≥800 687 800 4- Ø 16 ≥800 ≥800 Figure B-22 Installation positions of the expansion bolts for a single cabinet ú ú ∅ 4- 16 ú ú...
  • Page 26 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Table B-4 Determine installation hole positions based on the template Step Operation Remarks Put the marking template on the floor Figure B-24 shows the as required. marking template.
  • Page 27 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation The depth of the holes should range from 52 mm to 60 mm (2.0 in. to 2.4 in.).All the holes should have the same depth. Clean the holes before measuring their net depth, and then measure the hole depth.
  • Page 28 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Caution: You must insert the alignment rib of expansion nuts into the alignment grooves of expansion tubes first; otherwise you will be unable to install or fasten the expansion bolts.
  • Page 29 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Caution: The washers used to level the cabinets should be installed between the insulation plates and the floor. Insulation will fail if you install the shims between the insulation plates and the cabinets.
  • Page 30 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Connecting plate for combining cabinets Figure B-27 Position of the connecting plate To combine the cabinets, remove the connecting plates from the cabinet, and then reinstall the connecting plates to combine the two adjacent cabinets, as shown in Figure B-28.
  • Page 31 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Nut M8 (2) Flat washer 8 (3) Combined screw M6x12 (4) Spring washer 8 (5) Bolt M8x30 (6) Connecting plate for combining cabinets Figure B-28 Install the connecting plate for combining cabinets IV.
  • Page 32 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Figure B-29 Install a single cabinet on the cement floor Figure B-30 Install a row of cabinets on the cement floor B-31...
  • Page 33: Installing Cabinets On Antistatic Floor

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation V. Verifying installation The following requirements must be satisfied: Cabinet arrangement, installation positions, and directions must satisfy the requirements of the construction design. The front, back, left, and right surfaces of the cabinets should be perpendicular to the floor.
  • Page 34 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Upper support (2) Antistatic floor height scale (3) Lower support (4) Hole through which the support is installed on the ground (5) Holes connecting guide rails Figure B-31 Outline of N800 series supports Four types of components are available with the N800 series, three of which are height adjustable and one is height fixed.
  • Page 35 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation N800 series IV assemblies are fixed supports. They apply to ultra-high and ultra-low floors. The lowest applicable floor height of this assembly is 100 mm. II. Guide rails Holder-guide rail components include holder, holder fixing piece, and guide rail.
  • Page 36 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Figure B-33 Side holder Holder fixing pieces are installed under guide rails. They are used to connect guide rails and front/back holders, as shown in Figure B-34. Figure B-34 Holder fixing piece Guide rails are used to connect cabinets and supports.
  • Page 37: Installation Procedure

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Holes used to connect with supports (2) Holes used to connect with cabinets Figure B-35 Dimensions of the guide rail III. Quantity of supports and guide rails 2 ×...
  • Page 38 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Start Position supports Install supports Install guide rails and antistatic floor accessories Put the cabinet in position Level the cabinet Combine cabinets Combine cabinets Fix the cabinet Fix the cabinet...
  • Page 39: Positioning Supports

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Note: The procedure of combining cabinets is optional. When two or more than two cabinets need to be installed in the same row, they should be installed side by side.
  • Page 40 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation ú ú 690 800 ∅ 4- 16 ú ú Figure B-37 Installation hole positions of the support for a single cabinet ú ú ∅ 4- 16 ú ú...
  • Page 41 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Table B-7 Determine installation hole positions based on the marking template Step Operation Remarks Put the marking template on the floor as Figure B-39 shows the required. marking template.
  • Page 42: Installing Supports

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation The depth of the holes should range from 52 mm to 60 mm (2.0 in. to 2.4 in.). All the holes should have the same depth. After drilling a hole, use a dust collector to clean the dust inside and outside the holes before measuring the hole depth.
  • Page 43 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Caution: You must insert the alignment rib of expansion nuts into the alignment grooves of expansion tubes first; otherwise you will be unable to install or fasten the expansion bolts.
  • Page 44 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Height-retaining bolt (both sides) (2) Height-retaining bolt (middle) Figure B-41 Fix a rack onto the floor III. Assembling supports and guide rails Table B-9 Assemble supports and guide rails...
  • Page 45 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Support (2) Guide rail (3) Bolt M12x30 (4) Spring washer 12 (5) Flat washer 12 Figure B-42 Assemble supports and guide rails IV. Fixing supports Table B-10 Fix supports...
  • Page 46 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Bolt M12x60 (2) Spring washer 12 (3) Flat washer 12 (4) Expansion tube (5) Expansion nut Figure B-43 Assemble supports and guide rails In case of combining a row of cabinets, you must adjust the positions of the supports before fixing them.
  • Page 47: Installing Antistatic Floor Accessories

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.3.5 Installing Antistatic Floor Accessories Holders are used to support the antistatic floor around the cabinets. Holder fixing pieces are used to fix holders. Fix holder fixing pieces together with guide rails before...
  • Page 48 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Bolt M12x45 (2) Spring washer 12 (3) Insulation plate (4) Washer (5) Flat washer 12 (6) Nut (7) Guide rail Figure B-46 Level and fix a cabinet III.
  • Page 49: Fixing Cabinets

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.3.7 Fixing Cabinets I. Fixing anchor strips Table B-13 Fix anchor strips Step Operation Fix spring washers on bolts M12x45. Big washers and insulation coverings have been installed in the cabinet.
  • Page 50 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Connecting plate for combining cabinets Figure B-47 Position of the connecting plate Remove the connecting plates from the adjacent cabinets, and then reinstall the connecting plates, as shown in Figure B-48.
  • Page 51: Testing Insulation

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Nut M8 (2) Flat washer 8 (4) Spring washer 8 (3) Combined screw M6x12 (5) Bolt M8x30 (6) Connecting plate for combining cabinets Figure B-48 Install the connecting plate for combining cabinets B.3.8 Testing Insulation...
  • Page 52 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Cabinet (2) Guide rail (3) Support (4) Bolt M12x30 (5) Spring washer 12 (6) Flat washer 12 (7) Front holder (8) Holder fixing piece (9) Side holder Figure B-49 Install holders II.
  • Page 53: Verifying Installation

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Cabinet (2) Antistatic floor Figure B-50 Cabinets installed on the raised antistatic floor B.3.10 Verifying Installation The following requirements must be satisfied: The positions of the cabinets must comply with the construction design.
  • Page 54: Installing Cabinet Accessories

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.4 Installing Cabinet Accessories This section introduces how to install the cabinet accessories. The accessories include feet, doors, and protection ground cables. Caution: Install the feet after unpacking the cabinets and before putting the cabinets in the upright position.
  • Page 55 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Lower enclosure frame (2) Plastic cap Figure B-51 Remove plastic caps Install feet. B-54...
  • Page 56 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Lower enclosure frame (2) Cabinet foot (3) Flat washer 6 (4) Spring washer 6 (5) Bolt M6x16 Figure B-52 Install cabinet feet Remove the plastic shims and steel shims in the holes on the lower enclosure frame, and then fasten the feet on the lower enclosure frame.
  • Page 57: Installing Doors

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Cover plate (2) Lower enclosure frame Figure B-53 Install cover plates B.4.2 Installing Doors I. Introduction to doors Cabinet doors include side panels, front doors, and back doors, as shown in Figure B-54.
  • Page 58 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Front door (2) Side panel (3) Rack Figure B-54 Cabinet components II. Installation preparations Preconditions The preconditions of installing cabinet accessories are shown as follows: The cabinets have been fixed.
  • Page 59 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Side panels are necessary for both ends of a row of cabinets. Side panels fall in left ones and right ones. A pair of side panels needs to be installed at both ends of a row of cabinets.
  • Page 60 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Table B-15 Install a front/back door Step Operation Hold the door so that the cross-pin on the rack is in line with the hole at the lower right side of the door and then put the lower part of the left side also in position.
  • Page 61: Installing Protection Ground Cables

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Note: Hook pins have been installed on the doors before delivery. After installing the front door, stick the product label in the concave position of the front door.
  • Page 62: Introduction To Cabinet Cable Management

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation front side, back side, left side, and right side of the lower part of the cabinet respectively. Install the protection grounding cables after installing the cabinet doors. B.5 Introduction to Cabinet Cable Management This section introduces cable management for N68 cabinets, including introduction to the cabinet grounding points and internal cable management.
  • Page 63: Introduction To Cabinet Power Distribution

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation II. Main grounding point Main grounding point used to connect the cabinet and the equipment room is located on the cabinet top. The specification is M8, as shown in Figure B-59.
  • Page 64 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation I. Power distribution diagram for an N68 AC cabinet Figure B-60 Power distribution diagram for an N68 AC cabinet B-63...
  • Page 65 If your device power is small, the device is protected by its own power protection set or the superior air breaker rather than the NCB. You can change the NCB, but H3C does not provide NCBs of various capacities.
  • Page 66 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation II. Power distribution diagram for an N68 DC cabinet Figure B-61 Power distribution diagram for an N68 DC cabinet B-65...
  • Page 67: Introduction To Internal Cable Management

    If your device power is small, the device is protected by its own power protection set or the superior air breaker rather than the NCB. You can change the NCB, but H3C does not provide NCBs of various capacities.
  • Page 68 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Cabling brackets Figure B-62 1U cabling frame 2U cabling frame, which functions similarly as a 1U cabling frame while supporting a larger number of cables. It is mostly used for data cables. Following a similar...
  • Page 69 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Cabling brackets (2) Oval cable opening Figure B-63 2U cabling frame Note: You can move the positions of the 1U and 2U cabling frames as required. If necessary, you can also remove the adjacent dummy panel to facilitate cabling.
  • Page 70 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Cabling holding hook (2) Cable binding hole Figure B-64 1U rear cable management bracket Mounted at both sides of the cabinet, cable retaining brackets are used for management of bundled cables inside the cabinet.
  • Page 71 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Figure B-65 Cable retaining bracket Note: You can move the positions of cable retaining brackets in the cabinet required. For the specific method, refer to Figure B-66. B-70...
  • Page 72 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation (1) Tapping screw (2) Cable retaining bracket Figure B-66 Move a cable retaining bracket To move a cable retaining bracket, remove the tapping screw from the cable retaining bracket, move the cable retaining bracket to the desired position in the cabinet, and fasten the cable retaining bracket with the same tapping screw.
  • Page 73 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Cabling holes on the lower enclosure frame (1) Rear cabling hole (2) Corner cabling hole Figure B-68 Cabling holes on the lower enclosure frame B-72...
  • Page 74: Remodeling Cabinets

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.6 Remodeling Cabinets B.6.1 Remodeling an S7500 N68-18 Cabinet Figure B-69 Remodel an S7500 N68-18 cabinet B-73...
  • Page 75 In AC cabinets, no M10 exists, and the position is for the AC power distribution component. The S7500 series and other devices that comply with the N68 cabinet size can be installed in the cabinet. You do not need to use the cabinet exactly as the figure shows, but can adjust the positions of guide rails and dummy panels as needed.
  • Page 76 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Remodeling standard configuration to configuration B: Remove dummy panels M3 and M4, and remove guide rails C1 and C2. The result of the remodeling is configuration B. Remodeling standard configuration to configuration C: Remove dummy panels M3,...
  • Page 77: Remodeling An S7500 N68-22 Cabinet

    Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation B.6.2 Remodeling an S7500 N68-22 Cabinet Figure B-70 Remodel an S7500 N68-22 cabinet B-76...
  • Page 78 In AC cabinets, M13 does not exist, and the position is for the AC power distribution component. The S7500 series and other devices that comply with the N68 cabinet size can be installed in the cabinet. You need not to use the cabinet exactly as the figure shows, but can adjust the position of guild rails and dummy panels as needed.
  • Page 79 Installation Manual H3C S7500 Series Ethernet Switches Appendix B N68 Cabinet Installation Remodeling standard configuration to configuration B: Remove dummy panels M2 and M3, remove guide rails C1 and C2. The result of the remodeling is configuration B. Remodeling standard configuration to configuration C: Remove dummy panels M2, M3, M7 through M10, and remove guide rails C1, C2, G1 and G2.

Table of Contents