Screw the screws into the dowels.
Attach the supply and return lines (system connections, see Fig. 1 on page 7).
Check all screw connections to ensure they are secure.

5.3 First commissioning

Essential
y
HKF 8180 is fully installed.
Connecting the energy supply
Connect the HKF 8180's energy supply.
The electrical installation of HKF 8180 must only be performed by a qualified professional.
@
The HKF 8180 switches on automatically once the power supply has been connected.
Vent the heating system.
Switch the circulating pump off during the venting process.
Thermometer handle settings
A
Fig. 6: Thermometer handle settings
A
Operation setting: gravity brake ready for operation; ball valve open
B
Drain setting: gravity break open
C
Service setting: ball valve closed