Victoria CLASSIC 40C Instruction Manual

Pellet boiler

Advertisement

Quick Links

INSTRUCTION MANUAL
for installation and operation of pellet boiler
CLASSIC 40C

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CLASSIC 40C and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Victoria CLASSIC 40C

  • Page 1 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C...
  • Page 2: Table Of Contents

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C CONTENTS INTRODUCTION................................... 3 2.SAFETY INFORMATION................................3 3.TECHNICAL DATA AND DIMENSIONS............................4 4. INSTALLATION OF EXTERNAL ASHTRAY........................... 5 TECHNICAL DATA AND PERFORMANCE: ............................6 5. SAFETY DEVICES..................................7 6.
  • Page 3: Introduction

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C 1. Introduction. We congratulate you on the excellent choice! Do not leave this instruction manual unread. Installation and operation of a pellet boiler associated with various legal obligations, which are explained in this instruction manual. According to the laws and regulations for safe use of appliances of this class, the purchaser and user of the pellet boiler undertake using this instruction manual to inform themselves for the assembling and the right operation of the appliance.
  • Page 4: Technical Data And Dimensions

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C • Keep this instruction manual, warranty card and purchase invoice in good condition, as will be necessary in any inquiries. After shut down, do not burn the pellet boiler again before cleaning the combustion chamber! Removed pellets from the combustion chamber should not be placed back in the pellet fuel hopper! 3.Technical data and dimensions.
  • Page 5: Installation Of External Ashtray

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C 4. Installation of external ashtray. The construction of the pellet boiler allows mounting of the ashtray in left side or right side. Фиг.1.1 1. Pellet boiler 2. Bracket 3.
  • Page 6: Technical Data And Performance

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Technical data and performance: Classic 40C Pellet boiler class Input power 40 kW Nominal heat output 36 kW Reduced heat output 10 kW Operating water pressure 1.5 bar Maximum water pressure 2.25 bar...
  • Page 7: Safety Devices

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C 5. Safety devices. Fume thermocouple: It is placed at the top part of the heat exchanger Thermo-limiter: To prevent overheating of the system, with manual reset. Measure the temperature of the water into the integral boiler.
  • Page 8: Components

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C 7. Components. Ignition: Performs ignition of the pellets. Fume extractor: Provides the flue gases from the combustion chamber to the flue pipes and combustion air intake by vacuum...
  • Page 9: Fuel

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C The ash from the combustion process is conducted in an ashtray underneath the combustion chamber. Through built-in circulating pump (position H in fig. .2.1) hot water passes from the integral boiler to the heating system. The filling and emptying of the heating system is carried out via a shut-off valve.
  • Page 10 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Positioning: To have well operation the pellet boiler should be leveled. The floor on which is placed the pellet boiler must be of non-combustible materials (concrete, terrazzo, marble, terracotta, etc.).
  • Page 11 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Fig.4. Fig.5 А - Insulated metal chimney. В - minimum height of the vertical section 1.5 m, as the end of the chimney has to be completed in accordance with Fig. 5 С...
  • Page 12 The installation diagram is indicative and does not replace the documentation for the construction of the heating system made by an authorized person or company! Trained and competent technicians must make hydraulic connections. It’s allowed to make and other inspections in accordance with applicable country national laws where pellet boiler will be installed and used.
  • Page 13: Appliance Operation

    Before ignition, check: power, door seal, if the combustion chamber is cleaned and whether the display is switched to standby mode. 11.2. Control panel description. After start up, on the control display is shown the logo of Victoria-05 for 3 seconds and then switches to main user panel. The icons and functions are shown as follows: 11.2.1.
  • Page 14: Types Of Modes Of The Control Unit

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Important Features: - the minimum possible temperature that can be set is 55 ° C; - the maximum possible temperature that can be set is 80 ° C.
  • Page 15 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Here one can change the operation mode of the Smoke Fan. Should one chose Turns, then the fan would transfer to Set the Power Mode. Should one chose Flow, then the Fan would transfer to Flow Supervise Mode.
  • Page 16 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Information. In the Information Section one can supervise the operation of the sensors, to check the operation mode, etc. Smoke Gases indicates the Chamber Temperature.  Water Heater indicates the Water-heater Water Temperature.
  • Page 17 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C The tickboxes from 12 to 16 should be left empty (non-ticked). Meaning that through the hours from 12:00 to 16:00 it will not operate. The boxes 17 and 21 should be ticked.
  • Page 18: Service Technician Settings

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C 1. Type. Option - No feed. Meaning that no outside pellets feed is on. - Vacuum. Pellets Feed from an outside bunker, via a vacuum cleaner. - Screw Conveyor. Pellets...
  • Page 19: Instruction Manual

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Cycle. On how long passed time the system will do the cleaning. The time is in minutes. The setting is from 10 to 1440 360 min. minutes. For instance:...
  • Page 20: Wood Pellet Refueling

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C 12.2. Wood pellet refueling. When the pellet fuel hopper is completely empty, it means that the screw auger is also empty. Before re-ignite the pellet boiler is necessary to load it with wood pellets.
  • Page 21: Maintenance

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C The first one to start is P5, followed by P4 and in the end P1. Switching among these is based on the temperature, preset as water heater temperature.
  • Page 22: Weekly Cleaning

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C - Vacuum the combustion chamber and all contact edges; - Clean the glass when it is cold. If necessary, use appropriate detergent. Never vacuum hot coals, because this may damage it! 13.2.
  • Page 23 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Do not unplug the pellet boiler from the main electrical supply during process shutdown! Occurring an alarm event, there is the Alarm Icon showing on the Main Screen.
  • Page 24: Checklist

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C IRS Sensor Malfunction at input Ain2. Problem with temperature sensors of upper bulffer and Boiler Sensor lower buffer. Battery Low Low battery of the control unit. Reverse Combustion 15.
  • Page 25 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C What settings does the control panel of pellet boiler need? Setting the desired temperature of the water in the heating system. Pellet boiler will regulate the power to that temperature.
  • Page 26 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C...
  • Page 27 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C PRODUCT FICHE 1. Supplier's name or trademark. Victoria-05 Ltd. 1B Ivan Momchilov Str. 5100 Gorna Oryahovitsa Republic of Bulgaria Phone: +359 618 60200 E-mail: info@v05.bg http://www.v05.bg 2. Supplier's model identifier.
  • Page 28: Spare Parts Catalogue

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C SPARE PARTS CATALOGUE № Appellation Gear motor FB 1304 8rpm,52W - auger Gear motor FB 1218 3rpm,26W – fire grate cleaning and flue pipes cleaning Gear motor FB 1146 5,3rpm,52W – auger of the external ashtray Smoke extraction fan SIT - PL30CE0010 (set) Auger (set) for hopper - 192.00.10.00 ЧС...
  • Page 29: Warranty Conditions

    Failing that provided, the claim is not accepted as valid and the buyer pays repair. On the territory of Bulgaria the term of the removal of the claim is up to three (3) days for settlements in which Victoria-05 Ltd.
  • Page 30: Diary

    05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C DIARY for repairs under warranty № Company Receipt date Type of repair Delivery date Carried out...
  • Page 31 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C...
  • Page 32 05.2020 INSTRUCTION MANUAL for installation and operation of pellet boiler CLASSIC 40C Victoria-05 Ltd. 1B Ivan Momchilov Str. 5100 Gorna Oryahovitsa Republic of Bulgaria phone: +359 618 60282 fax: +359 618 60200 e-mail: info@v05.bg http://www.v05.bg...

Table of Contents