III-A. Included Components and Parts

The following items are included with your load bank. If any of the following are not included, please
contact Simplex Direct, Inc., at 800-637-8603.
1. Load bank
2. Manual
3. Human-Machine Interface (HMI)
4. Electrical drawings package

III-B. Primary Inspection

Preventative visual inspection of the shipping crate and the load bank is advised. Physical or electrical
problems due to handling and vibration may occur. Never apply power to a load bank before
performing this procedure. The following five-point inspection is recommended before installation
and as part of a 6-month maintenance schedule or as a load bank is relocated:
1. If the crate shows any signs of damage, examine the load bank in the corresponding
areas for signs of initial problems.
2. Check the entire outside of the cabinet for any visual damage, which could cause
internal electrical or mechanical problems due to reduced clearance.
3. Inspect all relays and control modules. Make sure all components are secure in their
bases and safety bails are in place. Spot check electrical connections for tightness. If any
loose connections are found, inspect and tighten all remaining connections.
4. Examine all accessible
internal electrical components
such as fuses, contactors, and
relays. Check lugged wires at
these components.
5. Visually inspect the element
chamber for foreign objects,
broken ceramic insulators,
and mechanical damage.
Atlas | Operation and Installation Manual
If any problems are observed
during primary inspection,
call Simplex 24 hours a day at
800-637-8603
8

Unpacking -

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Atlas and is the answer not in the manual?

Questions and answers

Table of Contents