ABB Totalflow G5 Series Application Manual page 16

Flow computers component replacement instructions
Hide thumbs Also See for Totalflow G5 Series:
Table of Contents

Advertisement

2.
Carefully move the IMV up into the access cutout.
3.
Place the split washer, then the flat washer on the screw and screw into the
mounting plate and up into the corresponding screw hole.
4.
Repeat step 3 for the remaining mounting screws.
5.
Securely tighten all eight mounting screws to keep out external environmental
elements.
6.
If the enclosure was previously rotated to allow for removing the IMV, rotate the
enclosure back to its original position:
a.
Using a ½ inch hex socket with ratchet, loosen the enclosure mounting
clamp bolts and rotate the enclosure back to the original position.
IMPORTANT NOTE: Manifold and tubing connections, power
application, and unit startup will be addressed in the startup guide
included in this kit. Complete the remaining procedures in this guide
before beginning startup procedures.
b.
After rotation, tighten the clamp bolts to hold the µFLO in place.
7.
Follow the procedure in section 3.4.2, Reinstall the I/O expansion board, on
page 8, if previously removed.
8.
Reconnect the following, if disconnected, to the µFLO
a.
LCD display cable from J8 connector.
b.
Communication connections:
-
MMI communication cable plug from J9
-
USB cable plug from J4
-
Ethernet cable plug from J1
c.
Field wiring connections:
-
Communication wiring from J10
-
DI wiring from J12
-
DO wiring from J13
-
RTD sensor from J3
This completes replacement of the IMV assembly. Begin startup procedures as
detailed in the Startup guide included in this kit. If necessary, follow instructions,
located in the user manual, listed under Additional information, to restore station
configuration files.
16 | 2105514-001 rev. AB
G5
electronic board:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Totalflow mflo g5Totalflow microflo g5

Table of Contents