The collectors of the FKA series are marked with the environmental label RAL-UZ-73 folar solar collectors („Blauer Engel“). The STI GmbH is obliged to take back the products which are marked with the environmental label RAL-UZ-73 for solar collectors and to...
Safety regulations, instructions and guidelines The standards and guidelines applied at the installation location of the collectors have to be considered in the latest release. Standards and guidelines Notes prior to the installation start • VBG 4 Unfallverhütungsvorschriften Elektrische The installation and initial operation must be carried out by Anlagen und Betriebsmittel an expert who is responsible for the correct installation and •...
Page 4
(e. g. STI Drain Master or SolBox) is recommended. Please pay increased attention to the possible durability of the screw fittings to fasten the collectors as well as to the It is necessary to pay attention that the back flow quality of the substructure.
Tools The following tools are needed for the assembly of the collectors: Cordless screwdriver Angle grinder Pencil Knife Drill Chalk box Folding yardstick Hammer Securing devices, protec- Roof ladder tive equipment...
Product description Solar collector FKF The solar thermal collector FKF uses the radiant energy of the sun to heat a heat transfer medium. This glycol-water mixture gives off the heat to a storage via a heat exchanger. The obtained energy can be used for water heating and heating support.
Page 7
Loss of pressure (T=20°C / 30l/h) 6.141 Pa 8.522 Pa 11.217 Pa 4.082 Pa 6.297 Pa 7.988 Pa Hydraulic system of the absorber FKF 200 H FKF 200 V FKF 240 V FKF 270 V FKF 240 H FKF 270 H...
Collector field dimensions Vertical section across a collector field In case of multi-row installations, the collectors will always be mounted Lip (Collector covering) on joint on top of each other. The lip (collector covering) of the upper collector has to be put onto the lower collector.
Page 9
Collector field dimensions Collector type 200 V Number of collectors Field width in mm 1.167 2.387 3.607 4.827 6.047 7.267 8.487 9.707 + 1.220 Number of rows Field height in mm 1.713 3.426 5.139 6.852 8.565 10.278 11.991 13.704 + 1.713 each additional collector 200 H Number of collectors...
Pipe routing by Tichelmann In case of multi-row installations as well as installations which include the STI Drain Back System, the connection pipe must always be connected with the diagonal line to the external manifold (Tichelmann), e. g. bottom left and top right.
Collector field sectional drawing Vertical cross section of the collector field Single-row collector field Ridge sheet If there is no lath Lead sheet available in this area Eaves sheet which serves as a support, you have to assemble it. Multi-row collector field Ridge sheet Eaves sheet Lead sheet...
Assembly preparation - sequence Single-row collector field When assembling single-row collector fields, the collectors will be mounted starting with the respectively outer collector. The exact assembly of the collectors will be described starting with page 29. Single-row collector field Assembly sequence Multi-row collector field When assembling mulit-row collector fields, the collectors which are located one above the other will be mounted first of all.
Page 13
Assembly preparation - sequence Assembly sequence Lip (collector covering) In case of multi-row installations, the collectors have to be mounted adjoining. The lip (collector covering) of the top collector is set over the lower collector. The lip (collector covering) of the lower collector is clamped into the joining area which guarantees an optimum waterflow.
Assembly of the intermediate plates/ multi-row collector fields Multi-row collector fields To attain a homogenous appearance of the collector installation, the assembly of sheets between the collectors is possible. The intermediate plates are exclusively assembled due to optical aspects and do not have a functional impact on the installation.
Page 15
Assembly of the intermediate plates By removing the lip (collector covering) at the prepared point the subsequent assembly of the intermediate plates and lateral sheets will be enabled. When assembling the upper collector it is necessary to pay attention that the collector frame of the lower collector is covered by the upper collector.
KVZ 40 x 60 mm 1440104 FKF 200/240/270 V L= 1,2 m 1440112 FKF 200 H L= 1,7 m 1440103 FKF 240 H L= 2,1 m...
Page 17
Assembly of the solar collectors Uncovered roof area with construction lath. Fixation with chipboard screws (3 pieces per lath). Placement of the first collector. The exact alignment and fixation happens after laying on and connecting of all collectors. Before the following collector can be layed down the hydraulical collector connector must be mounted at the concisely overhanging collector connection.
Page 18
Assembly of the solar collectors After placing the first collector the following collector is placed at a distance of 10 to 20 cm beside the first collector. The hydraulic collector connector must be mounted now on the first collector. Afterwards the following collector must be carfully pushed until the hydraulic collector connectors engage into the collector connection.
Page 19
Assembly of the solar collectors On the outside is the collector mount by three connection plates. If the collector fixing point is on a picket kick, a adiitional roof lath must be mounted below. On the mounting must be on the additional roof lath.
Page 20
Assembly of the solar collectors This procedure will be repeated for every single solar collector and all mounting plates. After having placed the last collector it has to be fixed with the outer fastening plates at three points. 1400103 collector fastening set built-in 2014 1910101 tool set 2014 Fastening plates Completely mounted and fixed collector row.
Assembly of the probe Every collector is equipped with a sheath for the positioning of a temperature sensor. The position of the temperature sensor is located below the upper left manifold outflow or to the left of the sticker with the label „above“...
Collector connections The cap will be mounted everywhere where a collector connection is not used. 1310209 Cap set (2 pieces complete) 1310119 Cap set aluminium (2 pieces complete) Connection 3/4“ 1310205 Collector connection set R3/4“ (2 pieces complete without cap) Connection for soldering or clamping ring transition 1310204 Collector connection set 22 mm (2 pieces complete without cap)
Overview hydraulic connections SLS / accessories Hydraulic connections copper Exhauster connection Collector connection 22 mm Collector connection 3/4“ For the installation at the for soldered fittings or clamping for thread fittings collector with extension ring joints Smart Lock System Smart Lock System Smart Lock System Collector connection hydraulic Clamp collector connection and...
Please be aware that only the connecting pipe DN20 l = 15 m can be adjusted individually. Any other corrugated pipe lines from stainless steel of the STI programme will be delivered in fixed lengths. 1320304 Connecting pipe DN20 l=15 m,...
Assembly eaves sheet Preparation Before starting the assembly of the plate set the collector field must completely be installed hydraulically, rinsed, bled and tested for leak tightness. Stop possible defects before starting assembly of the plate set. Subsequent installation or checking is not possible when the sheets are mounted. Start the assembly of the plate set starts definitively with the left eaves sheet.
Page 28
Assembly eaves sheet Check, before mounting the lateral sheets, if the eaves sheet has an overhang distance of 10 cm from the collector. If necessary, adjust. 10 cm Where the lateral sheet has an overhang fixate the eaves sheet with a nail at the maximum of 8 cm from the top. Where appropriate, a additional rail has to be mounted.
Page 29
Assembly eaves sheet Eaves sheet extension or eaves sheet right When mounting more than two collectors in one row, install the eaves sheet extension. Depending on the number of collectors as many extensions as needed are installed for all collectors. Finally install the eaves sheet right. The eaves sheet right is pushed under the sealing lip and clicked into the groove of the collector profile.
Page 30
Assembly eaves sheet Depending on the number of the collectors the next eave plate extensions and accordingly the eave plate must be mounted and fasten on the right side. Fully assembled eaveplates. If the installation of collectors on roofs with flat roof, for example, slate, shingle or Prefa, can be installed to support the eave plate can be installed an additional lath under the eave plate.
For the collector types FKF 200 V, FKF 240 V and FKF 270 V, two distance metal sheets are mounted in every gap between the collectors. For the collectors FKF 200 H, FKF 240 H and FKF 270 H, the assembly of one distance metal sheet is planned.
Assembly lateral sheet Lateral sheets In the next step the lateral sheets will be mounted. They are distinguished for the assembly on the right or the left side as well as for the lateral eaves sheet on the top or below. In case of vertical collectors use two lateral sheets per row (left and right).
Page 33
Assembly lateral sheet Pay attention that the lateral sheet is flush with the bent edge of the eaves sheet and that it is placed in the appropriate groove in the collector profile under the sealing lip (entire length). Before fixating the lateral sheet check if it is in a parallel position to the collector (10 cm).
Page 34
Assembly lateral sheet Subsequently, the upper lateral sheet is mounted. Ensure that the lateral sheet is placed within the groove in the collector profile under the sealing lip (entire length). Push the upper lateral sheet in that way that the lower one is always overlapped.
Assembly ridge sheet Assembly dimensions support sheet & ridge sheet connection bottom part FKF 200/240/270 H 200/240/270 V Collektor Measure FKF 200/240/270 V 400 mm 800 mm FKF 200 H 355 mm 710 mm 1.065 mm 1.420 mm FKF 240 H...
Page 36
Assembly ridge sheet Completely pre-assembled support sheets and bottom parts of ridge sheets. Start on the left side when mounting the ridge sheets. First insert the ridge sheet on the left side into the left lateral sheet. Afterwards, the ridge sheet is pushed over the sealing lip.
Page 37
Assembly ridge sheet Completely mounted ridge sheet left. The support sheets for the next collector are already mounted and fixed. Insert the next ridge sheet in the previous one. Proceed in the same way with every following collector. The last collector in a row has to be completed with the ridge sheet on the right side.
Page 38
Assembly ridge sheet Finally, stick the supplied sealing wedges on the lateral and ridge sheets directly next to the seam. Ensure that the ground (sheet) is dry, dust and dirt free during the whole application! Depending on the type of roof covering the application of the sealing wedges may not be necessary.
Pipe dimension of the con- necting pipe Recommended pipe dimension of the connecting pipe Length of pipe F + BF up to 10 m from 10 m from 15 m Number of collectors to 15 m to 20 m 2 coll. - 132 L/h 12 x1 15 x 1 15 x 1...
Page 40
Pipe dimensions of the connecting pipe Recommended pipe dimension of the connecting pipe Length of pipe F + BF from 40 m from 45 m from 50 m from 55 m Number of collectors to 45 m to 50 m to 55 m to 60 m 2 coll.
Initial operation Initial operation An annual review is recommended. The following components must be checked for proper function (if installed): After installing the other components such as flow pipe, return pipe, insulation, pump group, expansion tank and controller, the installation can be put into •...
Page 42
Initial operation Commissioning report Special Material Product Type Material Date of assembly feature tick accordingly (description) (Serial N°) Net surface Date of commissioning ...
Page 43
Initial operation Schematic drawing of the system construction and piping scheme:...
Page 44
Initial operation Schematic drawing of the system construction and piping scheme:...
Appendix Important to observe Any guarantee and warranty for collectors as well as for resulting damages on the system or building expires due to unauthorized changes on the collectors and the accessories. There is no guarantee or warranty due to optical or technical reduction or defects on the collector resulting from external influences, forasmuch as these influences are not part of the supplier’s sphere or influence and they are not explicitly known before execution.