3.2.2 Mounting when the transformer ratio measurement
is carried out after drying
1. Assemble the diverter switch housing and the tap selector
according to Section 3.1.3, steps 1 and 4-12.
2. Follow the instructions according to Section 3.2.1,
steps 5-13.
3. Attach the lifting device LL 136 016-D according to
Fig. 15.
The lifting device must be tilted when attaching.
Lift the tap-changer onto the yoke fork. Place the tap-
changer in position for mounting the outer shaft system
(see transformer drawing). Insert the supplied guide bolts
DS 7 and insulating bushings (not included in delivery) in
the lower flange; see Fig. 11. The guide bolts must fit into
the holes in the yoke fork and be secured by punch marks
in the pins. When the tap-changer is in place, remove the
lifting device.
4. Mount the conductors between the transformer winding
and the tap selector according to Section 3.3.
5. The tap-changer is now ready for drying together with the
transformer. Follow the instructions in Chapter 4.
22 Installation and commissioning guide UCL/VUCL | 1ZSC000562-AAZ en
Lifting device
Fig. 15. Attachment of lifting device.
Max. 90°

Advertisement

Table of Contents
loading

This manual is also suitable for:

VuclUcl seriesVucl seriesUcg seriesVucg series

Table of Contents