7.0 AC Power Director:

1. AC HFC power can be sent to remote locations via the output ports by installing a plug in fuse bar.
Figure 4 has no Fuse bar, therefore does not pass power.
2. Check the system maps to determine which ports should pass power. Install each fuse bar as
required. Refer to Figure 5.
Figure 4
8.0 General Set-up:
1. Test the optical input power on the system downstream cable with an optical power meter to verify
that it is within the optical input range specification.
2. Clean the optical connector on the node and on the service cable and connect them together.
3. Verify that the total upstream RF signal level (from all ports) is within the node's specified input range,
then connect the coaxial cable to the node's RF In/Out port.
4. The LBN200 must be grounded, Use a split-bolt grounding stud or your system preferred ground
attachment to ground the Node housing to earth ground. Install the split-bolt grounding stud on the
base housing. Refer to Figure 6.
• For a strand-mounted node, install the grounding stud in the threaded hole on the base.
• For a pedestal or surface mounted node, remove one of the two strand mount brackets,
and install the grounding stud in the threaded hole.
Loosen the top nut and insert the grounding cable. (You may need to remove the nut to insert cable.
With the grounding cable installed, tighten the top nut to secure the cable.
5. Apply HFC power to the node through power port (40 – 90VAC). Verify that the "Power LED" and the
"Opt. RX" LEDs illuminate.
Figure 6