Application Guide
Three Phase Sectionalizer
Solution 3
UTILITY VOLTAGE RESTRAINT WITH DOWNSTREAM RECLOSER
Customer Fault: Customer recloser cycles to clear fault and locks out, Voltage Restraint blocks
LBS count ... PME and Utility Feeder remain energized
Solution 4
INDUSTRIAL VOLTAGE RESTRAINT WITH DOWNSTREAM RECLOSER
Zone A Fault: RX1 cycles to clear fault and LBS locks out ... critical SWD continues.
Zone B Fault: RX2 cycles to clear fault, Voltage restraint blocks LBS count ... RX2 locks out
and critical SWD continues.