Page 1
MASSIVit 3D Printers 1800 Series Site Preparation Guide This document contains proprietary and confidential material of MASSIVit Ltd. Any unauthorized reproduction, use, or disclosure of this material, or any part thereof, is strictly prohibited. This document is solely for the use of MASSIVit employees and authorized MASSIVit customers.
Page 3
The material furnished in this document is believed to be accurate and reliable. However, no responsibility is assumed by MASSIVit 3D for the use of this document or any material included herein. MASSIVit 3D reserves the right to make changes to this document or any material included herein at any time and without notice.
Table of Contents Introduction ............................... 4 About the MASSIVit 3D Printers site preparation ................4 Safety ................................5 General Precautions and Cautions ....................5 Fire Prevention ............................5 Waste Disposal ............................5 Materials Handling ..........................6 Personnel Safety Considerations ......................6 Accountability ............................
Page 5
Figure 7-European connection diagram ....................16 Figure 8-North America connection diagram ..................17 Table List Table 1-Dimensions and Weight ......................... 9 Table 2-Electrical Requirements ....................... 15 Table 3-Power Consumption ........................15 Table 4-Transformer specifications ......................16 Site Preparation Need help? Contact support@massivit.com Manual...
Introduction About the MASSIVit 3D Printers site preparation This document is intended to guide and assist you in preparing your site for the MASSIVit 3D 1800 Series printers and includes prerequisites regarding the various elements needed on site prior to installation.
In the event of system malfunction or of improper response to safety controls, suspend all operation of the equipment, and notify MASSIVit 3D’s Customer Support Department immediately. Fire Prevention Do not use water to put out a fire. Use water spray only to cool containers. Do not ...
Massivit Dealers and service personnel are not authorized to perform maintenance processes for the site electrical infrastructure and printer’s connections to this structure. Safe isolation of the printer from power prior to service operations shall be done according to the local regulation, and is under the customer responsibility.
Accountability Shipping and Handling MASSIVit 3D will deliver the machine packed and ready for shipment (sea or air) at the MASSIVit 3D site. Shipping from the MASSIVit Production site to the customer dock is the customer’s responsibility including insurance and taxes.
System Overview System Overview Printer Dimensions and Weight The MASSIVit 1800 Printer Length and Weight are specified in the attached layout drawing. 2200 mm 2600 mm 1640 mm 3000 mm Figure 1: Printer Dimensions drawing Site Preparation Need help? Contact support@massivit.com...
System Overview Machine Height Configurations Crating & transportation Printing The MASSIVit 1800 Printer Length and Weight are specified in the attached table and the layout drawing. Mode Dimensions L.W.H Weight 2500[kg] 3 x 2.2 x 2.6 [m] Printing...
System Overview System External Components The Massivit1800 system external components are: Figure 3- Machine layout External Connections The Printer is equipped with the following external connection interfaces: Figure 4: Interface Box Site Preparation Need help? Contact support@massivit.com Manual...
Site Requirements Site Requirements This chapter describes the site preparation required for the MASSIVit 1800 printer operation. Unloading Space A suitable unloading area must be prepared. This area should be easily accessible to the delivery truck and be of sufficient space to unload the crates in which the printer is shipped.
Final size of the room should be according to the machine drawings 150 [cm] 220 [cm] 620 [cm] 180 [cm] 300 [cm] Models In/Out 240 [cm] 670 [cm] Figure 5: Workspace Clearances Site Preparation Need help? Contact support@massivit.com Manual...
MASSIVIT 1800 printer. The MASSIVIT 1800 printer is equipped with a built-in fume extraction system but nevertheless the customer must ensure that the site and the area surrounding the MASSIVIT 1800 printer complies with all applicable local legislation and guidance relating to ventilation and Direct printer ventilation Capacity: 18 CFM (30 ...
Facility Requirements Facility Requirements This chapter describes the facility required for the MASSIVit 1800 printer operation. Electrical Infrastructure This section provides the electrical specifications of the Massivit 1800 printer. Every system may be adapted to the mains power voltage of the country of installation.
Δ 3x 208/240/480 +G Depend on input voltage,30KVA Secondary Y 3x400+N+G 25 A Table 4-Transformer specifications European connection diagram ( For all country with 3ph 380/400 VAC) Air connection European type Figure 7-European connection diagram Site Preparation Need help? Contact support@massivit.com Manual...
Pneumatic Requirements The supply of compressed air to the Massivit 1800 printer may be by way of a central air supply system, or with the use of a dedicated air compressor. In either situation, a wall- mounted air outlet will be required. This should have a quick-coupler fitting and be located near the MASSIVIT 1800 printer.
Memory – 16 GB DDR3 (3 x 2 GB) 1066 MHz fully-buffered ECC RAM Hard Drive – From 1000GB SATA hard drive Ports- USB (at least 2) Optical Drive – DVDRW Site Preparation Need help? Contact support@massivit.com Manual...
The location of these stations should be clearly marked and easily accessible so that they can be reached quickly if needed. These stations are available from companies that supply occupational safety equipment. Site Preparation Need help? Contact support@massivit.com Manual...
Appendix A: Site Preparation Check List Site Preparation Checklist Please complete the following checklist and submit it to your MASSIVit 3D representative. The MASSIVit 3D representative will review the checklist, and confirm whether all pre-installation requirements have been carried out as specified. The MASSIVit 3D representative must confirm the checklist and forward the signed checklist to MASSIVit 3D Customer Support.
Page 24
Is the flooring capable of safely supporting and ☐ ☐ evenly distributing the weight of the printer? ☐ ☐ Has the floor surface been properly leveled? Positioning of the equipment has been ☐ ☐ determined Site Preparation Need help? Contact support@massivit.com Manual...
Page 25
Is there is 3D modeling experience in your site? ☐ ☐ Do you have 3D SW in your site? ☐ ☐ Do you need MASSIVit Application Web training ☐ ☐ prior Installation on? General Comments: Site Preparation Need help? Contact support@massivit.com...
Page 26
Site Manager Name Site Manager Signature: Date: Support@Massivit.com Please send the signed document to including your Site name. Site Preparation Need help? Contact support@massivit.com Manual...
Need help?
Do you have a question about the 1800 Series and is the answer not in the manual?