Commissioning In - Scholl 26060 FB Operating Manual

Table of Contents

Advertisement

Hotplate 26060 FB - 26150 FB
Commissioning
1.
Before commissioning
Before putting into operation of the device following items have to be checked:
-
Shipping damages?
-
Indications on the rating plate have to match with the local public supply system.
-
All electrical protective measures have been carried out and serviceability has been checked.
-
All screwed connections are tight.
2.
At commissioning
During the putting into operation has to be checked:
Defect devices are not allowed to put into operation.
!
Instructions for use
Connect hotplate by means of safety plug to power supply system.
Device is ready for operation.
Turn thermostat to the temperature intended.
Control light glows. Heating up period to approx. 45 min.
After heating up period regulation works automatically.
The signal light goes out after heaving reached wanted temperature.
Don't touch hot device with unprotected hands !!!
STATE March 2010
-IN-
-IN-
12

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents