4.1 Standard Mounting

The following procedure outlines the steps necessary to install the switch:
1.
Mount the switch to the chamber where you want the switch to trip.
The switch should be mounted 90° from the indicator assembly to
insure optimum magnetic coupling.
2.
The float must be cycled past the switch in both directions to insure
that the switch will operate properly when put into service.
Example
Configurations:
LMS100 Mounted
on KM26 Magnetic
Level Gauge

4.2 Rod Mounting

OI/LMS100-EN Rev. A |
4
LMS100 Magnetic Level Gauge Switch
LMS100
(HI LEVEL
SWITCH)
KM26 MLG
LMS100
(LO LEVEL
SWITCH)
KM26 Chamber Rod Mount
LMS100 Rod
Mounting Hardware
Swivel Mounting Bolts
LMS100 Switch
LMS100
LS700 (LS Series)
LMS100 Mounted on
LS Series Mechanical
Level Switch
Note:
1.
KM26 chambers that are furnished with factory in-
stalled insulation blankets may have switches mounted
via special rod mount brackets to a factory installed
switch mount rod that is external to the insulation. (See
section 4.2)
2.
When mounting/adjusting rod mounted LMS100,
ensure that the mounting "ears" of the switch are
flush against the float chamber to allow proper switch
function. Also, be sure to tighten all mounting bolt
hardware once switch is correctly mounted into posi-
tion (figure 4.2)