Müba KAL 275 Structure And Use Guidance

Lifting jack

Advertisement

Quick Links

Structure and use guidance
The M
M lifting jack serves for lifting or lowering components
and loads with assembly works on building sites. Only vertical
loads (in the plumb line) must be carried.
With the lifting jack e.g. steel girders or wood purlins can be millimeter-exactly
aligned. The weight is turned up or down by means of crank within selflocking
spindle transmission. The lifting jack is equipped with swivel rollers, so that it
can be easily moved to the load bearing position when not carrying a load.
When loaded, it must (only) be moved in longitudinal direction, which enables
precise alignment of components.

General note

Only components in perfect status and original equipment may be used.
This must be checked before use. The lifting jack must not be used until
it has been repaired appropriately.
The lifting jack is to be used only according to the intended purpose.
Any other improper use is prohibited.
The rules for the prevention of accidents are to be observed.

Technical data

lifting height....................................1.10 - 2.75 m
with adapter ..................................1.36 - 3.00 m
light mass heading fork ..........36 x 21 x 11.5 cm
dimensions folded ..............1.59 x 0.81 x 0.60 m
load-bearing capacity ..............................600 kg
(In case of paired operation 2 x 450 kg = 900 kg)
weight ........................................................86 kg
crank, adjustable...... ..............Order no. 12361
adapter ....................................Order no. 12374
height 1.10 m - 2.75 m
heading fork
stand
crank
18.08.2014
Lifting jack
Typ: KAL 275
Order no. 12373
height 1.36 m - 3.00 m
adapter
load loop
load arm
spindle
spindle transmission
props
underframe
A-BAU
02054
geprüfte
Sicherheit

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the KAL 275 and is the answer not in the manual?

Questions and answers

Summary of Contents for Müba KAL 275

  • Page 1 Lifting jack Typ: KAL 275 Order no. 12373 A-BAU 02054 Structure and use guidance geprüfte Sicherheit The M M lifting jack serves for lifting or lowering components height 1.36 m - 3.00 m and loads with assembly works on building sites. Only vertical loads (in the plumb line) must be carried.
  • Page 2 Building up the lifting jack During erection and dismantling of the lifting jack, there is an increased risk of crushing for fingers and hands. The following steps should be performed by 2 people, and the compo- nents to be moved are to be touched and handled from the outside. Do not reach into gaps and hinge openings.
  • Page 3 Use and operation Important: heading fork • The lifting jack may be set up only on horizontal-even, capable of foundation. • The weight, e.g. a steel girder or a wood purlin, will be put on the heading fork of the lifting jack or hooked into the loop of the boom.
  • Page 4 Lifting a load off the ground A fundamental requirement for intended lifting with the lifting jack is the lifting jack carriage being below the load. If the load to be lifted is on the ground (in the picture a carrier HE-B 300 for example), this must be initially lifted by approx.
  • Page 5 Using two lifting jacks When using two lifting jacks in pairs, the maximum load bearing capacity increases to 2 x 450 kg = 900 kg If two lifting jacks are being used, these are to be positioned symmetrical to the centre of gravity, as far towards the end of the carrier (load) as possible.
  • Page 6 Before each employment is to be considered • Visual check of the lifting jack on complete assembly and functional test of the spindle transmission. • Defective or worn parts must be changed before using. • Examine the spindle, the spindle transmission as well as the bearings for sufficient lubrication: - lubricants of the spindle as well as the spindle transmission with machine fat - oils of all bearings...

Table of Contents