Geotextile Sand Filter British Columbia Design & Installation Manual Represented By: BWD Engineering Inc. Surrey, BC Tel: 604-957-3611 www.bwdengngineering.com February 2019 www.eljen.com CORPORATION Innovative Onsite Products & Solutions Since 1970...
Page 2
Note: Please make sure you are using the most current version of this manual by going to www.eljen.com...
Page 6
Infiltrative Surface Sequential Distribution *See also SPM-V3, Volume I, Section 1.1 Glossary...
Page 8
Cover fabric substitution is not allowed Note: If modules are spaced end-to-end in trench applications, fabric must be cut and allowed to drape over and protect the ends of each spaced module. A continuous run of geotextile fabric is not allowed for these applications.
Page 11
Note: When pumping to D-box do not exceed D-box manufacturer’s maximum flow rate...
Page 17
all perforated holes not discharging at least 15 cm onto a GSF module must be sealed.
Page 18
PAINTED STRIPE FACING UP all perforated holes not discharging at least 15 cm onto a GSF module must be sealed. Note: If modules are spaced end-to-end, fabric must be cut and allowed to drape over and protect the ends of each spaced module.
Page 19
Note: Refer to Figure 12 for Design Illustration. Note: If modules are spaced end-to-end, fabric must be cut and allowed to drape over and protect the ends of each spaced module. A continuous run of geotextile fabric is not allowed for these applications.
Page 20
all perforated holes not discharging at least 15 cm onto a GSF module must be sealed. Note: If modules are spaced end-to-end, fabric must be cut and allowed to drape over and protect the ends of each spaced module. A continuous run of geotextile fabric is not allowed for these applications.
Page 22
NOTE: Half-pipe must cover any hole above the A42 module that is within 15 cm of the edge. If modules are spaced end-to-end, fabric must be cut and allowed to drape over and protect the ends of each spaced module. A continuous run of geotextile fabric is not allowed for these applications...
Page 23
Note: Middle cross-over pipes (not shown) are recommended for systems over 15 m (50 ft) long. Contact Eljen for Cross-Over pipe details if needed. Cross-Over and end loop pipes are not required on Pressure or Serial Bed Systems...
Page 24
Note: Do not end loop bed systems on slopes.
Page 27
COMPANY HISTORY COMPANY PHILOSOPHY CORPORATION www.eljen.com Printed in U.S.A. on recycled paper...
Need help?
Do you have a question about the GFS and is the answer not in the manual?
Questions and answers