INTRODUCTION: These instructions cover the setup of the Snapper Grounds Cruiser utility vehicle. Complete
each step carefully. A checklist has been provided. It is very important to verify and record each item on the
list prior to placing the machine into service. The dry weight of the machine you are about to setup is 1,230 lb. It
is strongly recommended that you use an overhead hoist when lifting the machine. The capacity of the device
used for lifting must exceed the weight of the machine. DO NOT work on the machine until properly blocked
and secured to prevent it from falling. If an overhead hoist is not available, you may have to remove boards
from the crate bottom to gain access with floor type jacks.
WARNING
DO NOT attempt any adjustments, maintenance or
service with the engine running. STOP engine. Set
park brake. Shift transmission to neutral and
remove key. Remove spark plug wire from spark
plug and secure wire away from spark plug. Engine
and components are HOT. Avoid serious burns,
allow all parts to cool before working on machine.
STEP 1
INSTALL REAR TIRES
The machine is securely attached to the crate bottom at
each wheel location. See Figure 1.1. The four steel
plates must be removed before lifting the machine. The
device used to lift the machine must have a capacity
greater than 1230 lb. The cargo bed is attached to the
frame of the machine with plastic straps. Carefully
remove the straps and set the cargo bed aside for
installation later.
REMOVE
FIGURE 1.1
1. Loosen only, two lug nuts at left and right rear
wheel hubs.
2. Remove the four bolts securing the left and right
support plates to the crate bottom.
3. Lift machine, at the rear hitch, only high enough to
allow tire installation. Block machine securely to
prevent it from falling. Remove support plates.
4. Check castle nuts to insure that the cotter pins have
been fully inserted and have at least one leg bent to
secure in place.
5. Install left and right rear tires and secure each with
6. Remove blocks and lower rear of machine.
7. Torque lug nuts to 75 ft-lb using sequence shown.
LUG NUTS
(LOOSEN ONLY)
STEP 2
INSTALL FRONT BUMPER
The bolts used to attach the front bumper to the
machine are already installed in the front frame. The
bumper can be used to lift the weight of the front of the
machine. The mounting hardware must be tightened
securely (30 ft-lb).
1. Place bumper over four bolts at front of frame. Note
2. Attach using (4) 3/8-16 flange lock nuts.
3. Torque nuts to 30 ft-lb.
1
5 lug nuts. NOTE: The tires are directional. Install
with valve stem out and the points of the chevron
treads pointing forward. See Figure 1.2.
1
4
POINTS OF TREADS POINTING TOWARD FRONT OF VEHICLE.
FIGURE 1.2
See Figure 1.2.
orientation, flat side of side plates towards bottom
INSTRUCTION No. 7-4510 (I.R. 5/3/01)
3
5
2

Advertisement

loading

Summary of Contents for Snapper 7-4510

  • Page 1 SETUP INSTRUCTIONS AND PRE-OPERATION CHECKLIST FOR SNAPPER GROUNDS CRUISER UTILITY VEHICLE INTRODUCTION: These instructions cover the setup of the Snapper Grounds Cruiser utility vehicle. Complete each step carefully. A checklist has been provided. It is very important to verify and record each item on the list prior to placing the machine into service.
  • Page 2 STEP 3 INSTALL FRONT TIRES The front bumper can be used to lift the front of the machine. Block the machine to prevent it from falling. NOTE: The front tires are directional. Install with valve stems out and with the points of the chevron treads pointing forward.
  • Page 3 STEP 6 INSTALL OPERATOR PROTECTIVE STRUCTURE (OPS) The installation of the Operator Protective Structure requires two people. The mounting hardware for the OPS and seat belts must be properly torqued. Do Not modify the OPS in any way. Install the OPS with the “WARNING”...
  • Page 4: Step 9 Install Steering Wheel

    STEP 8 (Continued) ACTIVATE BATTERY 8. Thoroughly clean any spilled acid from battery. Neutralize with Baking Soda and flush with large quantity of water. Dry off battery. 9. Install battery into power unit. Place battery into battery tray and secure in place with retaining rod. See Figure 1.5.
  • Page 5 STEP 10 (Continued) INSTALL OPERATOR’S AND PASSENGER’S SEAT (3) SEAT BOLTS HINGE ROD FIGURE 1.7 STEP 11 ATTACH CARGO BED Attach bed to pivots at rear of frame. A prop rod is provided to support an empty cargo bed only in a raised position.
  • Page 6: Operational Test

    Snapper has completed initial adjustments and performed operational tests prior to shipping the machine. Due to the possible effects of shipping, handling and storage, Snapper intends for all of the following items to be verified and necessary final adjustments made at time of setup. It remains good practice and is strongly recommended that all the items also be checked prior to placing the machine into service.

This manual is also suitable for:

Grounds cruiser