Caution: Protective safety clothing such as helmet, gloves, and steel toe shoes are recommended.
1.
Position the Ice Qube TMS so that the two mounting studs are in alignment with the top two 1/2" (12.7mm)
holes in your enclosure surface. (
2.
Slide the Ice Qube TMS mounting studs through the 1/2" (12.7mm) holes in your enclosure and check to see
that all openings are aligned.
3.
After checking that all opening and bolt holes are in alignment, assemble and tighten the (2) M10-1.5 nuts
and (8) M6-1 x 20mm bolts supplied with you Ice Qube TMS by hand. Check to ensure gasket will properly
seal the Ice Qube TMS to your enclosure.
4.
Using a wrench, tighten the nuts and bolts until the gasket between the air conditioner and the enclosure is
compressed to a maximum thickness of 1/8" (3.175mm). Check the entire perimeter of the gasket/enclosure
interface for compression and seal.
5.
Models that require maintaining a positive purge pressure or closed loop will require the condensate trap to
be filled. Carefully and slowly pour 20.0 ounces (600mL) of clean water into the drain pan located on the rear
of the unit. Look for label marking. Some water may drain from the condensate overflow nipple on the side
of the unit during this procedure.
6.
Mechanical installation is now complete. Continue with the electrical installation of the Ice Qube TMS.
7.
Connect external M6-1 x 20mm cabinet ground stud to secure earth ground (nut and wire terminal are
provided).
Ambient Side

Mechanical Installation Instruction

See Figure 1: Enclosure Installation pg:7)
Figure 1: Enclosure Installation
7
Enclosure Side
Rev. 1

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents