System Check Out And Operation - ADC BTS-7010 Technical Manual

Multi-channel (broadband) booster
Table of Contents

Advertisement

SYSTEM CHECK OUT AND OPERATION PROCEDURE
ELECTRICAL INTERFACE PROCEDURE
With the unit properly installed and adjusted in the equipment rack, the process of electrically interfacing
the transmitter can begin. The following steps should be completed:
INSTALL AC LINE CORD.
A line cord is provided with each BTS-7010 Unit.. Insert the female connector of the line cord into the
tray's AC input connector (J220). Make certain that the rear panel power switch is in the "OFF" position,
then plug the line cord into an appropriate AC outlet to power the unit.
An alternate hard wire input is provided at jack J221. This alternate AC input may be used to connect
directly to the system AC.
NOTE:
CONNECT RF OUTPUTS AND RF INPUTS:
Connect the output coaxial cables from the Bandpass Filter RF Outputs (J201-J204) to the transmit
antenna. Connect the UHF (222 to 408 MHz) output of the UHF tunners to the IF input of the BTS 1.0
(JJ231 – J234).
Connect the GPS antenna feed to the GPS Antenna input (J250). Connect 10 MHz input (J251) to 10
MHz reference if used.
The BTS-7010 was designed for 220 VAC 50/60 Hz. operation.
CAUTION:
Never remove the RF output coaxial
cables or otherwise unload the RF
outputs while operating. This may
cause harmful exposure to RF
radiation.