  • Page 1 SOLARWATT MYRESERVE QUICK INSTALLATION GUIDE...
  • Page 2 1x commissioning log, 2x instruction stickers indicating MyReserve switch-on and switch-off sequence 4) only included for MyReserve 500 (2.2 kWh) PAGE 2 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 3 2) 1x MyReserve installation and operating instructions, 1x MyReserve user manual, 1x commissioning log, 2x instruction stickers indicating MyReserve switch-on and switch-off sequence Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 3...
  • Page 4: Installation

    You will find more information in the detailed installation and operating instructions. PAGE 4 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 5 PV system (Q) into the housing from above. Be careful not to damage the cable inlet when doing so. cable inlet Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 5...
  • Page 6 Trim cable the upper battery module to the terminal strips. to 150  c m behind the cable inlet PAGE 6 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 7: Electrical Connection

    Only qualified electricians may put SOLARWATT MyReserve storage battery system into operati- on. There is a risk of electric shock. Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 7...
  • Page 8 Only qualified electricians may put SOLARWATT MyReserve storage battery system into operati- on. There is a risk of electric shock. PAGE 8 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 9 MyReserve extension battery cable (Extension 2.2 version) Black BAT- BAT+ Orange/white Orange/brown Yellow/green Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 9...
  • Page 10 10 mm insulated Gauge for the communication connection section 0.75 mm -2.5 mm insulated Single-phase connection Three-phase connection PAGE 10 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 11 The fuse protection for the voltage measurement lines may also be executed with a double tap on an existing circuit breaker if you comply with applicable standards and manufacturer specifications. Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 11...
  • Page 12 The top edge of the SOLARWATT MR Pack 2.2 must form a line with the leveling mark. PAGE 12 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 13: Connecting The Ground Cable(S)

    (I) that is included in the delivery to the un- used battery cable (the longer one of the two!). Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 13...
  • Page 14 The status LED on the front of the SOLARWATT MyReserve will now continuously light up in blue. PAGE 14 | Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH...
  • Page 15: Switching Off

    SOLARWATT AC Sensor 50 and 63 Energy management SOLARWATT Energy Manager DC current source Crystalline/amorphous SI photovoltaic modules Version: 01/2017 | SHORT INSTALLATION GUIDE | AZ-TM-PME-0697 | Rev. 012 | Subject to change | © 2017 SOLARWATT GmbH | PAGE 15...