UTICA BOILERS TriFire Assembly & Instruction Manual
UTICA BOILERS TriFire Assembly & Instruction Manual

UTICA BOILERS TriFire Assembly & Instruction Manual

Trifire oil fired boiler

Advertisement

This assembly must be completed by a qualified installer or service agency, in accordance with the
manufacturer's instructions, and in accordance with all codes and requirements of the authority having
jurisdiction. Failure to follow these instructions could result in fire or explosion resulting in property dam-

Knockdown Boiler Assembly Instructions -

TriFire Model
1.
Remove all components from crate. It may be to the
installer's advantage to place the cast iron boiler block
close to where the final installation location will be.
2.
Install rubber grommets in rear top plate. Attach with
brass bolts and washers. See
Figure 1
Rear of boiler
KNOCKDOWN ASSEMBLY
Instructions for
TriFire Oil Fired Boiler
!
age, personal injury, or loss of life.
Figure
1.
WARNING
3.
Wrap insulation around boiler with the smooth side out.
If necessary, overlap underneath boiler. Wrap 2 band-
ing strips around insulation. As shown in
Cinch banding together with plastic buckles provided.
Cut off excess banding material.
Insulation straps with buckles
1
P/N 240007211, Rev. A [04/08]
Figure
Figure 2
2,

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TriFire and is the answer not in the manual?

Questions and answers

Summary of Contents for UTICA BOILERS TriFire

  • Page 1 KNOCKDOWN ASSEMBLY Instructions for TriFire Oil Fired Boiler P/N 240007211, Rev. A [04/08] WARNING This assembly must be completed by a qualified installer or service agency, in accordance with the manufacturer’s instructions, and in accordance with all codes and requirements of the authority having jurisdiction.
  • Page 2 KNOCKDOWN BOILER ASSEMBLY Attach pipe nipples to supply and return outlets. Be Place the control panel on the top of the boiler with the sure to use pipe dope before screwing into boiler. See burner wire harness on the right. See Figure Figure 3.
  • Page 3 KNOCKDOWN BOILER ASSEMBLY Place the side jackets on the bolts from the previ- Attach the front control panel with the screws provided. ous step. Be sure to route the burner wire harness as Check the clearance between the two side panels and en- shown in Figure sure there is the same clearance top and bottom.
  • Page 4 KNOCKDOWN BOILER ASSEMBLY Attach the top panel with the screws provided. Proceed to the section “Packaged Boiler Assembly” in the Installation, Operation and Maintenance manual. For technical assistance with this product call toll free 1-800-325-5479 ECR International PO Box 4729 Utica, NY 13504-4729 www.ecrinternational.com...

Table of Contents