(800) 935-4002 | DIAMONDBACKCOVERS.COM
INSTALLATION GUIDE
75 minutes
Normal Install Time
PARTS INCLUDED:
Cab & T Panels Assembly
Tailgate Panel
TOOLS REQUIRED:
Drill
3/8" Nut Driver
PREPARE THE CARGO BED & POSITION THE COVER
Place the cab & T panels assembly on the front half of the bed so
1
its leading edge lines up with the leading edge of the bulkhead.
Slide the tailgate panel onto the T panel by mating their hinges.
2
Close the tailgate panel slowly while while holding the lock handle
in the open position.
To avoid hinge damage, do not close the
panel until the hinges are fully mated: Tilt
the panel past 90° and push to the left until
the hinge locking tabs interlock and the
hinge barrels are aligned with the leaves.
Place two cap clamps as far apart
4
as possible at each of the three
ends of the T panel. Tighten with
a 9/16" socket to 25 ft.-lbs.
Install the included bulkhead
5
weatherstrip now. Refer to the
Bulkhead Prep Kit Installation
Guide for details.
Keep an eye out for these icons:
Gas Springs (6)
Ratchet Wrench
9/16" Socket
Mating hinges is
easiest when you
line up the longer,
left hinge pin first.
IMPORTANT!
Important installation information
Self-Drilling
Grommets (2)
Screws (6)
Cap Clamps (6)
7/16" Socket
1/8" Hex Key
3
Center the DiamondBack
side to side.
2005-UP TOYOTA TACOMAS
with the 60.3" Bed
Helpful Hints
Tips to assist installation
PRE-INSTALLATION
NOTES:
If you are installing a Cross
Bin, you should start that
before you install the
DiamondBack 270. Refer to
page 2 of the Cross Bin
Installation Guide for details.
1/8" or
1" Bit
Marker
3/16" Bit
The bottom halves of the
cap clamps should fit into
the deck rail system.
Retorque your cap
clamps after 100 miles.
CONTINUED ON OTHER SIDE
Need help?
Do you have a question about the 270 and is the answer not in the manual?
Questions and answers