1. Drive the winch or tractor slowly so the tower will rise gradually, stopping every 15° to
check the tension of the guy-wires on both sides.
balanced, either too loose or too tight, please lower the tower slowly and adjust the
length of the guy-wires accordingly. Once balanced SIDE guy wire tension is
established, keep pulling until the tower stands upright. Separate the cord and fix the
FRONT guy-wire to the front anchor, then the BACK guy wire to its anchor. Be sure all
four guy wires have even tension.
2. Check and adjust the tension of each guy-wire so that they are evenly balanced. The
tension should not be too tight or too loose. Guy wires that are too tight may cause the
tower to bend, while being too loose may cause the tower to be unstable.
 
Installation of a Tapered Tower 
Step 1:  Choosing Installation Sites 
Please refer to the installation specification of guyed tower (step 1)
 
Step 2:  Make the Concrete Base 
Refer to the following graphs with the different product models.