Pentair Raychem NGC-UIT2-0RD Installation Instructions And Specifications page 3

User interface terminal for raychem ngc systems

Advertisement

cut opening and Mount nGc-uit2-orD on front of panel
1. locate the nGc-uit2-orD on front of panel
Locate the NGC-UIT2-ORD assembly on the front of the
panel at a level convenient for viewing. Make sure the cover
on the back of the assembly will not interfere with existing
panel hardware.
9.588 in
note: Cutting the opening for the display is a craft sensi-
tive procedure; if it is not done correctly, the panel door
can be damaged. The procedure for laying out and cutting
the opening for the display must be undertaken with
care, and by personnel qualified and experienced in panel
construction.
2. prepare and mark the position of the display opening and
mounting holes
• Use the cut-out directions to lay out the opening for the
NGC-UIT2-ORD display.
• Apply two layers of masking tape around the outer pe-
rimeter of the intended opening to prevent scratching the
panel surface with the jigsaw.
3. cut the display opening
Cut the opening for the NGC-UIT2-ORD with a jigsaw using
a 24 TPI blade. Take care not to damage the panel door.
Remove all rough edges and burrs with a metal file before
proceeding.
4. Drill the mounting holes
Drill the 12 holes with a #16 (3/16 in) drill bit to mount the
NGC-UIT2-ORD assembly in the panel.
note: The following steps are most easily accomplished if
the panel door is on a horizontal surface.
5. Mount the user interface assembly onto the panel door
• Place the NGC-UIT2-ORD assembly in position; the twelve
studs go through the twelve holes on the NGC-UIT2-ORD
assembly mounting plate (see figure below).
INDUSTRIAL HEAT TRACING SOLUTIONS
Cutting
Area
GB-RaychemNGCUIT20RD-IM-H58531     INSTALL-168      05/15
• Place the supplied 6/32 in Kep nuts on each of the twelve
mounting studs. Fasten only hand tight.
• Look at the front of the panel, and align the NGC-UIT2-
ORD assembly so it is level (loosen nuts if necessary to
reposition the NGC-UIT2-ORD assembly).
• After the display is properly positioned, tighten the nuts
to 0.9 newton-meters (8 inch-pounds) of torque using a
8 mm (5/16 in) in-line torque wrench. Do not overtighten
and risk damage to hardware.
• tighten Kep nuts in the sequence shown for proper
sealing.
Panel door
NGC-UIT2-ORD display
with sealing gasket
NGC-UIT2-ORD
display
Inside of
panel door
NGC-UIT2-ORD
display
Inside of
panel door


