13 CASING ASSEMBLY - continued
Complete the following after reaching Frame 32
15. Fit the lower top panel.
Fit the lower front panel.
16. The upper front panel has 2 hooks at the bottom.
Drop in these 2 hooks behind the back edge of the
lower top panel, push home onto the 4 catches and
secure with the top screw.
17. Fit rear panels in the sequence shown. Do NOT
tighten the screws until all panels are fitted.
Fit No.1 panel with the top 2 screws only.
Fit No.2 panel with the bottom 2 screws only.
Fit No.3 panel with the 4 screws engaging panels 1 and 2.
Fit No.4 panel with the 4 screws.
Align all panels and tighten all screws.
14
INSTALLATION
9. Route the overheat thermostat capillary through the cable clips as
shown.
Ensure the phial is correctly seated in the correct pocket opposite
side to the flow connection - refer to Frame 8.
Secure with the split pin provided.
10. Ensure that the Heyco bush is correctly located
and that the top of the bush is at the marked line.
Route the cables from the temperature probe, air
pressure switch and float switch through the clips
on the RH side panel.
Neatly coil up any excess length of cable and
push in the plug-in connector into the connection
box.
11. Hook the upper side panel into the keyhole slot.
12. Fix the upper side panel in position.
One screw into the lower side panel, one screw
into the upper support angle.
Repeat for the other side.
13. Clip in the upper top panel.
Fit the infill panel around the flue and secure
underneath top panel with the 2 self tapping
screws provided.
14. Fit earth leads as
shown.