Installation Guide
a tower or placed on the ground. It is recommended that only one RRU be installed on angle
steel.
Prerequisite
Before you install an RRU on a tower, the RRU and mounting kits are hoisted onto the tower.
For details, see
The hoist clamp on the main mounting bracket is secured properly.
Context
Figure 6-28
Figure 6-28 Top view of the RRU
(1) Angle steel
Procedure
Step 1 Determine a position for installing the main mounting bracket.
l
l
Issue 05 (2011-10-20)
6.6 Hoisting the RRU and Mounting Kits onto a
shows the top view of the RRU installed on angle steel.
If the RRU must be installed on a tower, see
RRU
to determine a position.
If the RRU must be installed on the ground, see
Figure 6-29 Distance between the main mounting bracket and the ground
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Tower.
3.5.1 Installation Clearance for a Single
Figure 6-29
to determine a position.