1. Purge gas, hot water and cold water supply lines before making the final connection of
the water heater. Swarf in either the gas or water supplies may cause damage.
2. Turn on gas and cold water supplies.
3. Test for water leaks and gas escapes near the unit.
4. Isolate gas and electric supply. Remove test point screw located on the inlet gas
pipework below the heater and attach pressure gauge.
5. Turn the power on at the switch and turn on gas. Warning: There are 230V AC live
supplies inside the heater.
6. Turn the water heater on with control panel; select the maximum delivery temperature
and open ALL available hot water outlets. (CAUTION: Ensure building occupants do not
have access to hot water outlets during this procedure).
7. The gas pressure check must be carried out with all other appliances on the same main
operating at maximum capacity to ensure that there is sufficient gas pressure.
8. With all appliances on the same main operating at high fire check the pressure at the test
point on the inlet to the gas valve. The pressure must be within the local defined limits for
the type of gas that is being used. If the pressure is lower, the gas supply is inadequate
and the water heater will not operate to specification. Check gas meter, regulator and
pipework for correct operation/sizing and rectify as required. Note that the gas regulator
on the appliance is electronically controlled and factory pre-set. Under normal
circumstances it does not need adjustment during installation.
The gas pressure must be at least 20 mbar for G20 Natural Gas as used in UK.
For G31 Propane as used in the UK the pressure must be at least 34.5 mbar.
9. Close hot water outlets.
10.Inspect and clean the strainer and the filter located on the cold water inlet pipe. This
procedure may need to be repeated to ensure the strainer remains clear.
11.Test control panel operation through the complete range of functions.
12.Confirm the hot water delivery temperature using a thermometer; compare the measured
value to the set point on control panel.
13.After testing is completed, explain to the user the functions and operation of the water
heater and control panel.

TESTING

25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Reu-1110ffu(f)-eReu-1412ffu-eReu-1412ffu(f)-e

Table of Contents