START-UP

4.4.3
Command relay connection
i
Notes
The appliance is delivered pre-cabled.
2kW
4kW
1
control relay
4.4.4
Connecting the main circuit board
Refer to the "appendix" section.
4.5

Cableway and passage

Caution!
b
Risk of material damage
Comply with electrical cable
routing
Comply with the prescribed cable-
routing paths to avoid any contact
between the cable and the
surface of the heating coil.
When replacing the power cable,
tighten the cable's screwed
connection sufficiently to secure
the strain relief.
Strain relief: 100N (10kg)
i
Notes
The cables must pass through the openings
provided for this purpose.
12
1
N
L
L
L
N
1 2
1
2
3
2
2
resistance heater relay
cable
Installation instructions and instructions for use VWZ MEH 61 0020166663_03
2
1
8
5
8
1
Pressure sensor cable
2
Temperature sensor
cable
3
Circuit board power
cable
4
Resistance heater
control relay cable
5
Start-up
► Check the electrical and water installation.
► Check all connections for leaks.
► Fill the heating installation.
► Purge your heating system.
► Replace the power.
► To use the AI interface and confi gure the hydraulic
station, refer to the user and installer documents for the
aroTHERM heat pump.
Danger!
e
Risk of death from electric shock!
Before carrying out the following
3
4
5
6
7
5
7
5
Power cable
6
3 way-valve motor cable
7
High voltage systems
options cables
8
Low voltage systems
options cables

Hide quick links: