Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net 1 Introduction Assembling General information This equipment should be installed, inspected, maintained and operated in accordance with EN1176-7 guidelines. Before installation work commences, please check that you have all of the equipment and fixation components in the parts list provided (see Tables 3-1 and 3-2).
Page 4
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Drawings / Views All optical drawings are showing only the measurements/dimensions and are no mandatory technical views of the complete item. We reserve the right to change technical details of our articles which are serving for the further development of our articles and are reasonable for the customer.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Datasheet: Mini M-Swing, Art. 4540-10 Space requirement: 3.00 m x 0.80 m and/or 2,30 m x 6,30 m including safety zone, height of fall 1,45 m Required safety surface:...
Page 6
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net In case of sandy and soft soils, the surface measure of foundations have to be enlarged for about 50%! Assembly time, once foundations completed: 1/2 hour. Required assistants: 1 person.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Delivery contents (parts list with part numbers) In words Table 3-1: Delivery contents, in words Pos. Quantity Element / Size O.K. Missing Description Swing part Steel post Ø 100 mm - 2.40 m lg...
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net In symbols Table 3-2: Delivery contents, in symbols Pos. Quantity Symbol Ø0,90m Ø 100 mm - 2.40 m lg for Ø 101.6 mm M10 x 110 mm galv. M10 galv.
Page 14
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Version: Mini M-swing Setting time at least 7-8 days Concrete C25/30 (for foundations) Attention! Dt. 114 The hexagon socket at thew swing joint art. 4602 has to be pressed into the drilling holes by solid tightening of the hexagon nut (Pos.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Post Installation Checks If the equipment has not been installed safely, you must ensure that the public is prevented from using it. Marking filler depth Labelling the posts to show the depth of material provided as fall protection (i.e.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Introduction Maintenance General informations This equipment should be installed, inspected, maintained and operated in accordance with EN 1176-7 guidelines. Please note: Providing any necessary repairs are carried out, a piece of play equipment that is inspected regularly cannot become so damaged that it is dangerous.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net General maintenance information Maintenance intervals Maintenance intervals are based on average use. Please note that more frequent inspections and/or maintenance are required if the play equipment is subject to intensive use.
Page 20
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net 7.10 Faults Faults must be repaired as soon as they are detected. If serious defects that compromise safety cannot be repaired straight away, the public must be prevented from using the equipment with immediate effect.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Maintenance Timetable Special advices 8.1.1 Maintenance interval We strongly advise you to carry out inspections and maintenance work within the specified periods as use of the equipment, the weather and malicious vandalism cause wear and tear that compromises the safety and function of the equipment.
Page 22
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net Maintenance Timetable Special advices 9.1.1 Maintenance interval We strongly advise you to carry out inspections and maintenance work within the specified periods as use of the equipment, the weather and malicious vandalism cause wear and tear that compromises the safety and function of the equipment.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net 10 Monthly maintenance 10.1 Check the spaces between the equipment and the ground (clearance and height of fall). 10.2 Check the ground surface in the area with fall protection for hard objects and loose foundations.
Zinc paint should be applied to corroded areas and scratches. The equipment must be inspected by someone with the necessary expertise in strict compliance with the instructions issued by Huck Seiltechnik GmbH. A copy of the inspection record should be given to the operator, who must confirm receipt.
Huck Seiltechnik GmbH • 35614 Aßlar/Berghausen • Germany seiltechnik@huck.net • www.huck.net 15 Hand Over Document After the installation of the equipment pass the installation and maintenance documents to the operator. The operator has to receive the hand over documents. The complete filled and signed hand over document should be sent to the supplier.
Need help?
Do you have a question about the 4540-10 and is the answer not in the manual?
Questions and answers