Rig And Place Unit; Inspection; Installation; Select And Install Ductwork - Carrier 50JZ Installation, Start-Up And Service Instructions Manual

7-14 kw (024-048) single-package 50hz heat pump units with puron (r-410a) refrigerant
Table of Contents

Advertisement

CORNER WEIGHTS (SMALL CABINET)
Unit
Total Weight
Corner Weight 1
Corner Weight 2
Corner Weight 3
Corner Weight 4
carpeting or other combustible materials. Slab-mounted units
should be at least 4 in. (101.6 mm) above the highest expected
water and runoff levels. Do not use unit if it has been under water.
Step 4—Rig and Place Unit
Rigging and handling of this equipment can be hazardous for many
reasons due to the installation location (roofs, elevated structures,
etc.)
Only trained, qualified crane operators and ground support staff
should handle and install this equipment.
When working with this equipment, observe precautions in the
literature, on tags, stickers, and labels attached to the equipment,
and any other safety precautions that might apply.
Follow all applicable safety codes. Wear safety shoes and work
gloves.

INSPECTION

Prior to initial use, and at monthly intervals, all rigging brackets
and straps should be visually inspected for any damage, evidence
of wear, structural deformation, or cracks. Particular attention
should be paid to excessive wear at hoist hooking points and load
support areas. Brackets or straps showing any kind of wear in these
areas must not be used and should be discarded.

INSTALLATION

1. Remove unit from shipping carton. Leave top shipping skid on
the unit as a spreader bar to prevent the rigging straps from
damaging the unit. If the wood skid is not available, use a
spreader bar of sufficient length to protect unit from damage.
2. Position the lifting bracket assembly around the base of the
unit. Be sure the strap does not twist.
3. Place each of the 4 metal lifting brackets into the rigging holds
in the composite unit base.
4. Thread lifting bracket strapping around bottom perimeter of
unit as follows:
a. Open lever of tension buckle (ratchet type).
1
y
4
24
30
136
145
28.5
28.5
28
33.5
25
25
53.5
58
Fig. 4—Corner Weights (kg)
x
CORNER WEIGHTS (LARGE CABINET)
36
149
29
34.5
26
59
b. Feed strapping through tension buckle as shown in Fig. 8.
c. Pull strapping through tension buckle unit taut.
d. Snap lever down to lock strap in tension buckle. To release
strapping, squeeze safety latch, lift lever, and pull webbing
outward.
5. Tighten the tension buckle until it is taut. Lifting brackets
must be secure in the rigging holds.
6. Attach field-supplied clevis or hook of sufficient strength to
hole in the lifting bracket. (See Fig. 9)
7. Attach the 2 safety straps directly to the clevis or hook at the
4 rigging brackets. DO NOT attach the safety straps to the
lifting brackets. (See Fig. 9)
8. Position lifting point directly over the unit's center of gravity.
9. Lift unit. When unit is directly over the roof curb, remove the
2 safety straps. Lower the equipment onto the roof curb.
10. After the unit is placed on the roofcurb or mounting pad,
remove the top crating.
Step 5—Select and Install Ductwork
The design and installation of the duct system must be in
accordance with the standards of the NFPA for installation of
non-residence type air conditioning and ventilating systems, NFPA
90A or residence-type, NFPA 90B and/or local codes and ordi-
nances.
Select and size ductwork, supply-air registers, and return air grilles
according to ASHRAE (American Society of Heating, Refrigera-
tion, and Air Conditioning Engineers) recommendations.
The unit has duct flanges on the supply- and return-air openings on
the side of the unit.
When designing and installing ductwork, consider the following:
5
2
3
Unit
Total Weight
Corner Weight 1
Corner Weight 2
Corner Weight 3
Corner Weight 4
C00071
48
161
34.5
23
43.5
60