APPROVED FITTINGS
VENTING SYSTEM INSPECTION & INSTALLATION
BOILER IS TO BE VENTED BY NATURAL
DRAFT AND SHALL NOT BE CONNECTED
INTO ANY PORTION OF A MECHANICAL
DRAFT SYSTEM OPERATING UNDER A
POSITIVE PRESSURE.
INSPECT CHIMNEY to make certain it is
constructed according to the latest revision of
NFPA211. Local codes may differ from this code
and should be checked. Where there is a conflict,
the local code will prevail.
This boiler must be installed into a chimney which
has a masonry or metallic chimney liner.
VENTILATION & COMBUSTION AIR
coMBusTion air supplied
froM inside The Building
TYPICAL INSTALLATION SINGLE PIPE OIL SYSTEM WITH 2 OR MORE UNITS
SWING JOINTS
VENT PIPE
FILLER PIPE
OIL GAUGE
OIL TANK
OIL FILTER
WarNiNG
figure #4
REFER TO NATIONAL BOARD OF
MINIMUM
SHUT OFF VALVE
CLOSE
NIPPLES
TEES
OIL LINE MUST BE BURIED OR OTHERWISE
PROTECTED FROM DAMAGE. MINIMUM
.5" IPS OR 1/2" O.D. COPPER TUBING
RIDGE
11
FIRE UNDERWRITERS
figure #5
MORE THAN 10'(3.1 M)
10' (3.1 M)
HEIGHT ABOVE ANY
ROOF SURFACE WITHIN
10' (3.1 M)
HORIZONTALLY
2' (.61 M)
MIN.
CHIMNEY 3'
(.92 M) MIN.
GAS VENT OR
TYPE L VENT 2'
(.61 M) MIN.