Flue Elbow
Apply Lubricant for
ease of assembly.
Ensure Elbow is fully
engaged into Boiler
Adaptor
Apply the lubricant
supplied for ease of
assembly (do not use
any other type).
Ensure Flue is fully
engaged into Elbow
26
© Baxi Heating UK Ltd 2015
Adaptor
Fig. 27
Trims
Fig. 28
Flue to elbow
securing screws
Elbow to adaptor
securing screws
Slots at bottom
9.0 Installation
9.6
Fitting the Flue (Cont)
10. Remove the flue elbow and insert the flue through the
hole in the wall.
11. Refit the elbow to the boiler adaptor, ensuring that it is
pushed fully in (Fig. 27).
12. Two flue trims are supplied, one for internal use, the
other for outside. The internal trim is packaged and
identified as such - it should not be used externally.
13. It is recommended that if the internal trim is being used
it is first fitted over the elbow to allow access to the
securing screws and then manouvered into place against
the wall.
14. Draw the flue back through the wall and engage it in
the elbow. It may be necessary to lubricate to ease
assembly of the elbow and flue (Fig. 28).
15. Ensure that the terminal is positioned with the slots to
the bottom (Fig. 29). Secure the flue to the elbow with the
screws supplied (Fig. 28).
16. Secure the elbow flue to the boiler adaptor with the
screws supplied in the boiler fittings pack (Fig. 28).
IMPORTANT: It is essential that the flue terminal is fitted
as shown to ensure correct boiler operation and prevent
water entering the flue.
17. Make good between the wall and air duct outside the
building, appropriate to the wall construction and fire rating.
18. If necessary fit a terminal guard (see Section 8.4).
Fig. 29