CS300 BOILER INSTALLATION AND OPERATION INSTRUCTIONS
Figure 19
Marking Burner Base Rear Midpoint
Apply two coats of the spray adhesive supplied with the
boiler to the rope seal grooves, Figure 20. Allow time for
the first coat to become tacky before applying the second
coat.
CAUTION: Do not get any of the spray adhesive in
the seal ports or premature failure of the seals may
occur voiding the warranty!
Figure 20
Ceramic Rope Adhesive Application
When the second coat is tacky lay the rope seal into the
three rope groves and press in place. Trim the rope off
flush with the edge of the cast iron section. The rope
seal is to be applied only to one side of each cast iron
section, Figures 21, 22 and 23.
Figure 21
Figure 22
Figure 23
Ceramic Rope Application
Trimming Ceramic Rope
Casting w/ Ceramic Rope
Page 15